Project risk management system utilizing probability distributions
Abstract
When the process plan made for execution is corrected based on the process correction condition, the variation amount in each of processes based on the process correction condition is calculated as the probability distribution using the probability distribution data generated by obtaining the probability distribution from the variation-amount prediction value of each of the processes. Thereby, the influence degree on other processes when the process is corrected can be estimated not simply as the propagation of the variation fixed value but so as to be more suited to the actual circumstances in accordance with the attribute information and the past variation patterns of the process.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 17 · Forward citations: 25.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A project risk management system comprising: a process plan database that records work-process information defined by work information, including at least one information piece including work type, type of parts to be worked on, number of parts to be worked on, total weight of parts to be worked on, occupational category of workers, name of engineering work company, planned number of man-hours, planned construction period, weather during work, work area, presence/absence of scaffolding, use/nonuse of material handling device, and number of workers; a constraint condition database that records
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (15 of 25 total)
References Cited — Backward Prior Art (17)
Non-Patent Literature (5)
- Basu, Abhi, Practical Risk Analysis in Scheduling AACE International Transactions, 1998.
- Dawood, Nashwan, Estimating project and activity duration: a risk management approach using network analysis Construction Management and Economics, vol. 16, 1998, pp. 41-48.
- Dawson, R.J. et al., Practical Proposals for Managing Uncertainty and Risk in Project Planning International Journal of Project Management, vol. 16, No. 5, Oct. 1998, Abstract.
- Finley, Eric D. et al., Project Scheduling Risk Assessment Using Monte Carlo Methods Cost Engineering, vol. 36, No. 10, 1994, pp. 24-28.
- Hammond, Chris, @Risk arms Excel with Risk Analysis InfoWorld, vol. 22, No. 12, Mar. 20, 2000.