Patents
US 7,769,684 B2#9396680 Most CitedActiveUnited States (USPTO)Utility

Semi-quantitative risk analysis

11Forward Citations (#9396680 Global)
0.7/yrCitation Velocity (#11085731 Global)
2.13Citation PageRank (#13146560 Global)
18Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

A semi-quantitative analysis on the risk management process increases the possibility of performing an accurate risks comparison, making easier the identification of which risks shall be prioritized and shall receive the greatest mitigation efforts. Specifically, the semi-quantitative risk analysis enables an improved risks comparison for evaluating the consequences of each risk considering its impacts on the project's Net Present Value (NPV), reflecting the project's cash flow at different times. The use of such method makes the prioritization process more efficient, helping the managers and other personnel involved on the process to focus their efforts to the most critical risks for the project's success. In this sense, the risk management process becomes more efficient and better able to provide better support to the project decision makers.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 18 · Forward citations: 11.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A computer-implemented project risk assessment method comprising: a computer receiving and storing project data, wherein said project data defines the net present value (NPV) of a project over a time period; said computer identifying a plurality of project risks using said project data; said computer, for each of the project risks, defining an impact to the NPV and a probability of occurrence; said computer continuously prioritizing each of the project risks in real-time according to the risks' respective impacts to NPV and probability of occurrence; said computer continuously selecting th

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (4)

  • "Developing a risk management matrix for effective project planning-an empirical study", Sumit Datta, S K Mukherjee. Project Management Journal. Sylva: Jun. 2001. vol. 32, iss. 2; p. 45, 13 pages.
  • "Developing a risk management matrix for effective project planning—an empirical study", Sumit Datta, S K Mukherjee. Project Management Journal. Sylva: Jun. 2001. vol. 32, iss. 2; p. 45, 13 pages.
  • "Identifying, justifying and prioritizing technical projects", Jonathan Worstell, Jeffrey Worstell, John Worstel. Chemical Engineering Progress. New York: Mar. 2002. vol. 98 iss. 3: p. 72, 8 pgs.
  • "The application of risk management in Infrastructure Construction Projects", Ali, Rashed, Cost Engineering, Aug. 2005, v47n8 pp. 20-27.