System and method for modeling construction risk using location-based construction planning models
Abstract
A method for modeling construction risk is provided. The method includes providing a statistical model for each of a plurality of location-based tasks of a construction project model. A model parameter is randomly selected for each of the plurality of statistical models to generate a statistically-based duration for each of the location-based tasks. A schedule duration is then calculated using the statistically-based durations of the location-based tasks, and the steps of providing, randomly selecting, and calculating are repeated until a statistical distribution for the construction project model is generated, such as using a Monte Carlo analysis procedure.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 5 · Forward citations: 14.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A method for modeling construction risk comprising: providing a statistical model for each of a plurality of location-based tasks of a construction project model, wherein one of a plurality of work crews performs an associated one of each of the plurality of location-based tasks, wherein one of a plurality of first statistical models is related to a corresponding one of the plurality of work crews, and one of a plurality of second statistical models is related to a corresponding one location variable of each location-based task; randomly selecting a model parameter for each of the plurality of
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (14 of 14 total)
References Cited — Backward Prior Art (5)
Non-Patent Literature (5)
- Brenda McCabe, "Monte Carlo Simulation for Schedule Risks", 2003, Proceedings of the 2003 Winter Simulation Conference, pp. 1561-1565.
- I-Tung Yang et al. "Stochastic resource-constrained scheduling for repetitive construction projects with uncertain supply of resources and funding", available online Apr. 18, 2005, International Journal of Project Management, vol. 23, pp. 546-553.
- I-Tung Yang, "Stochastic analysis on project duration under the requirement of continuous resource utilization", Aug. 2002, Proceedings IGLC-10, Brazil, pp. 1-13.
- Iulian Trofin, "Impact of uncertainty on construction project performance using linear scheduling", 2004, University of Florida, pp. iii-xiii, 1-91.
- J.D. Lutz et al., abstract of Analyzing linear construction operations using simulation and line of balance, 1993, Transportation Research Board, pp. 1-3.