PROBLEM TO BE SOLVED: To improve a construction method for a concrete arch bridge so as to construct a long and large concrete arch bridge. SOLUTION: A synthetic arch lining construction method is used. A steel pipe arch rib 11 is formed so as to have a truss structure, concrete…
Ps Corp
PROBLEM TO BE SOLVED: To accurately correct changes in the form of precast segments sequentially manufactured using short line match casting method and to accurately and easily erect a bridge whose form is as designed by use of the precast segments whose form is thus controlled.…
PROBLEM TO BE SOLVED: To provide an engaging device easily and positively engageable with a prestressing bar in a single operation. SOLUTION: This engaging device 1 comprises a male cone 10 provided with an internal thread on the bore surface, having a conical taper at the outer…
PROBLEM TO BE SOLVED: To provide a construction method for cast-in-place overhang blocks for an overhang-erected girder of prestressed concrete construction using corrugated steel plate for web plate. SOLUTION: Stiffening frames 41, 42 restricting the deformation of a corrugated…
<P>PROBLEM TO BE SOLVED: To provide a continuous steel plate web bridge used for constructing elevated roads or bridges and a method of constructing the continuous steel plate web bridge. <P>SOLUTION: This continuous steel plate web bridge is constructed by…
<P>PROBLEM TO BE SOLVED: To provide a wind power generation hybrid tower having inertia force less increased in earthquake while retaining its rigidity. <P>SOLUTION: The wind power generation hybrid tower has a base end formed of prestressed concrete and a steel…
PROBLEM TO BE SOLVED: To improve such a requirement that a concrete cross section and the quantity of reinforcing bars must be increased to resist the bending stress applied to arch ribs at an earthquake in the method for constructing the arch ribs by suspending arch-shaped…
<P>PROBLEM TO BE SOLVED: To provide a main tower for a wind-power generation facility efficiently conducting transport of materials and assembly works. <P>SOLUTION: Since the wind-power generation facility is constituted by combining concrete elements divided in the…
PROBLEM TO BE SOLVED: To dynamically reasonably constitute a long pole-shaped wind power generating tower erected on the foundation and having a wind mill and a power generator on its top part by manufacturing the total tower body by one kind of a form, and combining…
PROBLEM TO BE SOLVED: To improve workability by providing reinforcing round steel bars having a screw type jack at the upper and lower edges of a corrugated steel plate web of a box-shaped girder provided with upper and lower concrete floor slabs. SOLUTION: Two rows of…
PROBLEM TO BE SOLVED: To make firm a joint part between a web steel plate and a concrete upper floor slab. SOLUTION: A joining device for a floor slab and web steel plate in floor system is characterized in that in a steel-concrete composite structure supporting the concrete…
PROBLEM TO BE SOLVED: To facilitate adaption to a change in gradient to lessen a burden of a temporary bracing by fixing a lateral main beam suspending three expansible rods by pin connection on an existing block, and connecting a constructing bed to a new block to the lower…
<P>PROBLEM TO BE SOLVED: To provide a steel-concrete compound beam used for constructing elevated roads or bridges and a method of constructing the steel-concrete compound beam. <P>SOLUTION: This steel-concrete compound beam comprises an upper flange formed of steel…
PROBLEM TO BE SOLVED: To provide a tentatively installed work scaffolding that is used when maintaining and inspecting a pedestrian overpass or a passengers' overpass, does not require any traffic regulation above and below a bridge, can be safely erected or eliminated, and…
PROBLEM TO BE SOLVED: To provide a widening PC floor slab structure that prevents a floor slab thickness from being increased and an RC structure part from being formed.SOLUTION: A widening PC floor slab structure 1 is for widening in a width direction an existing concrete floor…
PROBLEM TO BE SOLVED: To permit accurate winding of reinforcing wires without requiring a wide working area around a columnar structure to be reinforced by drawing out reinforcing wires from a rotation drum turning and rising around the columnar structure and reinforcing the…
<P>PROBLEM TO BE SOLVED: To provide a bridge installing device for shortening a construction period, by facilitating resuspension of a segment. <P>SOLUTION: This bridge installing device has an installing work vehicle capable of self-traveling on an existing beam,…
PROBLEM TO BE SOLVED: To absorb deviation caused by deformation of a joint by inserting reinforcements into bolt holes for connecting webs and embedding them into lining concrete when connecting bridge girders. SOLUTION: In bridge bodies 40a, 40b, a box-girder is formed with…
<P>PROBLEM TO BE SOLVED: To provide a reinforcing construction method for an existing floor slab by a beam, easy in maintenance of a floor slab, by reducing an increase in a dead load, without requiring traffic regulation in response to construction. <P>SOLUTION:…
PROBLEM TO BE SOLVED: To provide a prestressed concrete bridge structure capable of constantly detecting a state of tension in an outer cable, acquiring an increase in the tension and restoring load bearing capacity of the outer cable by reapplying the tension to the outer cable…
PROBLEM TO BE SOLVED: To provide a column-beam joint structure useful for labor saving of work on a construction site and shortening of a construction period, a column-beam joint method, and a precast concrete column head member.SOLUTION: In a column-beam joint structure 1 for…
PROBLEM TO BE SOLVED: To provide a precast floor slab erection machine that may be transferred without using a rail for traveling, even when there is a stepped part on an existing floor slab.SOLUTION: A precast floor slab erection machine 1 includes: a pair of gate-form frames 2…
PROBLEM TO BE SOLVED: To facilitate the placing of a traveling truck on a track in a direction changing side irrespective any changes in the inter-leg dimension of a bridge crane by the stopping position of the traveling truck. SOLUTION: This raveling direction changing device…
PROBLEM TO BE SOLVED: To provide a rational panel structure suitable for a steel concrete composite truss facilitating the manufacture and execution with a few sorts of the constituent components for the steel concrete composite truss. SOLUTION: A joint structure of the steel…
PROBLEM TO BE SOLVED: To provide a pre-stressed concrete truss beam for reducing member weights and a method for manufacturing the pre-stressed concrete truss beam.SOLUTION: Members such as an upper chord member, lower chord member, vertical member and diagonal member composed…