US 2006271420 A1#2917975 Most Cited · 26 citations1.3/yr · PR 2.40PendingUS · Application
System and method for performing capacity checks and resource scheduling within a supply chain management system

A system and method are described for performing bucket-oriented capacity checks on resources to determine whether activities can be processed prior to a desired delivery date. For example, a method according to one embodiment of the invention comprises: subdividing a supply…

US 2006143063 A1#6797889 Most Cited · 14 citations0.7/yr · PR 2.97PendingUS · Application
Systems, methods and computer program products for compact scheduling

Methods, systems and computer program products are provided for allocating resources in a plannable process, wherein a number of resources is used for executing an order comprising a chain of related activities to be executed on the number of resources. In one implementation, a…

US 2014172738 A1#13666959 Most Cited · 8 citations0.7/yr · PR 1.67PendingUS · Application
Knowledge based initialization for routing optimization

According to one general aspect, a method of transportation management may include receiving a request to transport a current freight unit from a current source location to a current destination location. The method may include selecting a prior shipment path based upon a…

US 8,321,258 B2#21198742 Most Cited · 5 citations0.4/yr · PR 1.43ActiveUS · Utility
Vehicle scheduling and routing with compartments

Embodiments of the invention include a system for scheduling the shipment of a set of products. The shipment may be loaded into a set of vehicles and further configured to fit a set of compartments on those vehicles. The system may include attempts to fill each vehicle and the…

US 2006184263 A1#33658215 Most Cited · 3 citations0.1/yr · PR 1.02PendingUS · Application
Identifying critical operations of a production process

Identifying an operation that is critical to meeting a due date of a production order includes identifying operations associated with the production order, obtaining schedules for the operations using infinite production planning, obtaining start intervals for the operations…

DE 112004001264 B4#38580068 Most Cited · 2 citations0.1/yr · PR 1.05ExpiredDE · Utility
Abschlagsmatte für einen Golfball
Inventors: Engelmann Thomas, Marcy Richard SAssignee: Engelmann Thomas, Marcy Richard SFiled 2004-07-24 · Granted 2007-04-12

Abschlagsmatte (1) für einen Golfball (2), aufweisend mindestens eine Dämpfungsschicht mit einer Abschlagsoberfläche, insbesondere Kunstrasenoberfläche, auf der mindestens ein Abschlagspunkt für den Golfball (2) markiert ist, dadurch gekennzeichnet, dass in, auf oder an der…

WO 2005/011822 A1#44127144 Most Cited · 2 citations0.1/yr · PR 0.91PendingWO · Application
Tee-off mat for a golf ball

The invention relates to a tee-off mat for a golf ball. Said tee-off mat comprises at least one attenuating layer with a tee-off top surface, especially an artificial turf surface, whereon at least one tee-off point is marked for the golf ball. According to the invention, means…

US 8,533,023 B2#88281757 Most Cited · 0 citations0.0/yr · PR 0.56ExpiredUS · Utility
Systems, methods and computer program products for compact scheduling
Inventors: Braun Heinrich K, Engelmann Thomas H, Hentschel Martin DAssignee: Braun Heinrich K, Engelmann Thomas HFiled 2005-12-29 · Granted 2013-09-10

Methods, systems and computer program products are provided for allocating resources in a plannable process, wherein a number of resources is used for executing an order comprising a chain of related activities to be executed on the number of resources. In one implementation, a…