Production of a tower
Abstract
The present invention relates to a method for producing a tower segment of a concrete tower of a wind energy installation, comprising the steps: providing a segment mold having at least one formwork for defining a mold of the tower segment that is to be produced and for filling with concrete; filling the segment mold with concrete in order to form the tower segment by the subsequent hardening of the concrete; measuring the tower segment thus hardened for creating a three-dimensional, virtual actual model of said tower segment; producing said three-dimensional actual model; comparing the three-dimensional actual model with a predefined mold, in particular a stored three-dimensional, virtual target model; and determining a deviation between both virtual models and changing the segment mold, in particular changing the at least one formwork when the deviation exceeds a first predefined threshold value.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 28 · Forward citations: 3.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A process for making pylon segments for a concrete pylon of a wind power installation, the process comprising: providing a segment mold having at least one shuttering for predetermining a shape of the pylon segments and for filling with concrete; filling the segment mold with concrete; hardening the concrete to form a first pylon segment; measuring the first pylon segment for the production of a three-dimensional virtual actual model of said first pylon segment; producing said three-dimensional virtual actual model; comparing the three-dimensional virtual actual model to a three-dimensional vi
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (3 of 3 total)
References Cited — Backward Prior Art (28)
Non-Patent Literature (3)
- Akinci, Burcu, et al. "A formalism for utilization of sensor systems and integrated project models for active construction quality control." Automation in Construction 15.2 (Mar. 2006): 124-138.
- Machine translation of EP 1 544 376 A2, Jun. 22, 2005.
- Rauno Heikkila et al., "Dreidimensionales Mess-Und Prufsystem Fur Die Produktion Architektonischer Betonfertigteile, Three-Dimensional Control System for Precast Architectural Concrete Production" BFT International, Bauverlag, Gutersloh, DE, Oct. 1, 1994, pp. 62-67.