Combined cycle power plant black start method where steam turbine provides increase in demanded load
Abstract
A reliable and flexible black start network restoration for a combined cycle power plant can be achieved by synchronizing a steam turbine and ramping that steam turbine up to an operating point where a maximum power increase is achieved. The resulting steam turbine load change can be compensated by the gas turbine. The increase in the demanded load can be provided by the steam turbine. The load of the steam turbine can also be gradually reduced to increase its load-increasing capacity.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 19 · Forward citations: 0.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A method for operating a combined cycle power plant during a black start, the combined cycle power plant comprising a gas turbine and a steam turbine that generate alternating voltage of an assigned frequency and deliver the alternating voltage to an AC network via an electric generator connected to the gas turbine and an electric generator connected to the steam turbine, wherein flue gas of the gas turbine is used for producing steam for the steam turbine for network restoration, the method comprising: a) supplying internal consumers by the gas turbine in island mode, an operating point of th
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (0 of 0 total)
No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.
References Cited — Backward Prior Art (19)
Non-Patent Literature (2)
- Office Action (First Office Action) issued on Feb. 28, 2015, by the State Intellectual Property Office of People's Republic of China in corresponding Chinese Patent Application No. 201210330022.5 and an English Translation of the Office Action. (16 pages).
- Yuanwang G et al., "Automatic Derivation and Assessment of Power System Black-Start Schemes", Automation of Electric Power Systems, China, vol. 28 No. 13, Jul. 10, 2004, pp. 50-54, p. 84.