Method for the mounting of underground pipelines
Abstract
A method for mounting pipelines (8) or outer walls of a tunnel in the ground where one after another joined polygon or round cylinders are forced to penetrate into the ground when the soil cut by the front edge of the first cylinder (2) moves into the said cylinders during tunnelling. The cylinders (2, 3, 4, 15) containing soil are replaced by the final pipe/piping (8) meant for the ground, by forcing and/or pulling said pipe/piping in the place of said cylinders and the soil excavated from the tunnel is removed from the tunnel inside the said cylinders when said cylinders are forced out of the tunnel.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 15 · Forward citations: 28.
Claims (3 — 1 Independent, 2 Dependent)
- Claim 1Independent Claim
A method of mounting pipelines or tunnels in the ground comprising the steps of: (a) forcing successively joined polygonal or round conduit sections each having front and rear ends, into the ground so as to penetrate the soil; (b) cutting and moving the soil cut by a front edge of a first conduit section into the conduit sections; (c) replacing the conduit sections with final pipe/piping by pushing and/or pulling said pipe/piping in place of the conduit sections; and (d) removing the conduit sections and the soil therein from the ground so as to remove the excavated soil.
- Claim 2Depends on #1
The method of claim 1 wherein conical lap joints are used to join the polygonal or round conduit sections.
- Claim 3Depends on #2
The method of claim 2 further comprising the steps of removing soil from said conduit sections and to loosen the conical lap joints be
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗