KR 100,895,033 B1#4477631 Most Cited · 19 citations1.1/yr · PR 4.01ActiveKR · Utility
Precasr pier unit and pier construction method therewith

본 발명은 프리캐스트 방식으로 기둥구조물을 시공하는 프리캐스트 기둥유니트 및 이를 이용한 기둥구조물 시공방법에 관한 것으로서 프리캐스트 기둥유니트와 프리캐스트 기둥유니트를 서로 중공슬리브 및 연결재에 의하여 간단하게 삽입하는 것만으로 서로 안전하게 결합시킬 수 있어 경제적이고 효율적인 기둥구조물 시공이 가능하도록 하게 된다. 프리캐스트, 기둥구조물, 적층

KR 100,689,091 B1#11012155 Most Cited · 9 citations0.5/yr · PR 3.89ActiveKR · Utility
Continuous bridge using hybrid girder
Inventors: Kim Sang Hyo, Ahn Jin Hee, Won Jung HoonAssignee: Ind Academic Coop, Yooho Dev & Construction Co LtFiled 2006-08-08 · Granted 2007-03-02

A continuous bridge using a hybrid girder is provided to have the optimum cross sectional shape and to reduce clearance by using the strong points of concrete and steel which are resistant to compressive stress and tensile stress and to utilize for various methods and spans by…

KR 20100099947 A#14292386 Most Cited · 7 citations0.4/yr · PR 2.82ActiveKR · Utility
Locking device for cover plates

PURPOSE: A deck plate fixing device is provided to prevent noise due to gap between a deck plate and a support beam and to prevent the deck plate from horizontally moving on a support beam. CONSTITUTION: A deck plate fixing device comprises a rod(130), a spring(150), a…

KR 20100009766 A#17306166 Most Cited · 6 citations0.4/yr · PR 1.77ActiveKR · Utility
Precasr pier unit using sheath and pier construction method therewith

PURPOSE: A construction method of a column structure using a precast column unit using a sheath pipe is provided to secure the adhesion performance between precast column units, and reduce the construction period. CONSTITUTION: A construction method of a column structure using a…

KR 100,689,090 B1#19120154 Most Cited · 5 citations0.3/yr · PR 2.90ActiveKR · Utility
Simple beam bridge using hybrid girder
Inventors: Kim Sang Hyo, Ahn Jin Hee, Cho Kwang IlAssignee: Ind Academic Coop, Yooho Dev & Construction Co LtFiled 2006-08-08 · Granted 2007-03-02

A simple bridge using a hybrid girder is provided to have the optimum cross sectional shape by having high resistance to compressive stress and tensile stress using the strong points of concrete and steel. The simple bridge using a hybrid girder(G) contains a steel section(10)…

KR 20090084376 A#20599607 Most Cited · 5 citations0.3/yr · PR 1.54ActiveKR · Utility
Composite girder used steel-concrete of continuous of prestress bridge and it's building method

A steel-concrete composite girder on the continuous point of a prestressed composite girder bridge and a construction method thereof are provided to resist efficiently the stress acting on the junction of the steel-concrete composite girder. A steel-concrete composite girder on…

KR 20090108150 A#19932862 Most Cited · 5 citations0.3/yr · PR 1.75ActiveKR · Utility
Hybrid fiber reinforced polymer panel and temporary structure construction method using the same

PURPOSE: A hybrid fiber reinforced polymer lining board and a temporary facility construction method using the same are provided to prevent the board from losing and to reduce a manufacturing cost by manufacturing the board with only fiber reinforced polymer material.…

KR 20100066691 A#23319717 Most Cited · 4 citations0.2/yr · PR 1.73ActiveKR · Utility
Precasr pier unit for footing level control and pier construction method therewith

PURPOSE: A precast column unit for a level control and a construction method of a column structure using the same are provided to securely and safely connect precast column units with excellent construction performance. CONSTITUTION: A precast column unit(400) for a level…

KR 20100089178 A#24962353 Most Cited · 4 citations0.2/yr · PR 1.36ActiveKR · Utility
Composite girder used steel-concrete and manufacturing method thereof

PURPOSE: A steel-concrete composite girder, with which the steel girder and shear connection part are integrally formed, and a manufacturing method thereof are provided to secure the convenience on construction by deleting a soldering process of welding. CONSTITUTION: A…

KR 20100089180 A#23374425 Most Cited · 4 citations0.2/yr · PR 1.71ActiveKR · Utility
Composite girder used steel-concrete

PURPOSE: A steel-concrete composite girder with a connection bracket for improving assimilability is provided to increase the rigidity of a steel-concrete composite girder by reinforcing the end part of a steel-concrete composite girder. CONSTITUTION: A steel-concrete composite…

KR 20090003807 A#27925014 Most Cited · 3 citations0.2/yr · PR 1.78ActiveKR · Utility
The continuous bridge structure including a prestressing plate and it's building method
Inventors: Kim Sang HyoAssignee: Ind Academic Coop, Big Star Construction Co LtdFiled 2007-07-03

A continuous support structure including a prestressing steel plate and the construction method thereof are provided to increase the effective cross section of a continuous support and to decrease the negative moment of a continuous support by applying compressive stress on a…

KR 20090084377 A#38277870 Most Cited · 2 citations0.1/yr · PR 1.07ActiveKR · Utility
Composite girder used stell-concrete for upper lower reinforcing endurance force of continuity of prestress bridge

A steel-concrete composite girder for reinforcing the upper and lower resistance load on the continuous point of a prestressed composite girder bridge is provided to increase drooping and bending resistance about the applied load because the composite section of the concrete…

KR 20100089181 A#62306491 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
Manfacturing method of composite girder used steel-concrete

PURPOSE: A steel-concrete composite girder manufacturing method using a connection bracket is provided to increase the load carrying capacity at the connection point of the steel-concrete composite girder monomer. CONSTITUTION: A unit in which steel-concrete is synthesized is…