Method and apparatus for installing, maintaining and decommissioning wind turbines, both onshore and offshore, comprises a crane having extendable legs that allow it to climb a tower that it is erecting in sections by engaging the tower by friction or mechanical interference.…
Willis Stewart
There is disclosed a variety of arrangements for laying of rigid pipe from reeled storage and/or on-board welding fabrication. Thirteen independent aspects of the invention are identified. In one particular arrangement (FIGS. 3 a - 3 b ), a tilting lay tower ( 106 ) having two…
There is disclosed a variety of arrangements for laying of rigid pipe from reeled storage and/or on-board welding fabrication. Thirteen independent aspects of the invention are identified. In one particular arrangement (3a-3b), a tilting lay tower (106) having two travelling…
There is disclosed a clamp, a self-advancing climbing device including two such clamps, and a method of coupling such a clamp to a tubular. In one embodiment of the invention, there is disclosed a clamp ( 1 ) for a tubular, in particular a thin-walled tubular such as the tower (…
Equipment and method for lowering equipment ( 10 ) to the seabed from a vessel ( 12 ) using man made fibre rope ( 16 ) and a winch ( 20 ) employing wire rope ( 24 ), the fibre rope being paid out (or when lifting, drawn in) in sections by repeated operation of the winch ( 20 )…
The invention relates to a pipe handling clamp ( 26, 28 ) for use on a deep water pipe laying vessel. The arrangement includes an array of piston members ( 60 ) constrained to move along, a first axis towards and away from a fixed support ( 40,42 ), and an hydraulically operated…
The invention relates to pipe handling apparatus for laying elongate articles, such as pipes ( 16 ) in deep waters. The apparatus includes a tiltable pipe handling structure ( 22 ) housing a travelling clamp ( 26 ) for holding and/or paying out under tension the elongate article…
Method and apparatus for installing, maintaining and decommissioning wind turbines, both onshore and offshore, comprises a crane having extendable legs that allow it to climb a tower that it is erecting in sections by engaging the tower by friction or mechanical interference.…
A pipelaying vessel comprises storage (502) for a number of pipe units to be assembled into a pipeline and S-lay apparatus (312, 314, 316) for fabricating and paying out of a pipeline by repeated addition of new sections (506). The end of said pipeline being laid is held aligned…
Described are structures, such as wind turbine structures for offshore sites, comprising transport elements configured for complementary mating with engagement elements of a clamp, which allow for transporting of the structures using that clamp. Generally, the transport element…
There is disclosed a variety of arrangements for laying of rigid pipe from reeled storage and/or on-board welding fabrication. Thirteen independent aspects of the invention are identified. In one particular arrangement ( FIGS. 3 a -3 b ), a tilting lay tower ( 106 ) having two…
There is disclosed a clamp, a self-advancing climbing device including two such clamps, and a method of coupling such a clamp to a tubular. In one embodiment of the invention, there is disclosed a clamp (1) for a tubular, in particular a thin-walled tubular such as the tower (3)…
This invention relates to apparatus and methods for laying of elongate articles from a vessel. The vessel includes a tower (2), on which is supported tensioning means (20,21), straightening means (19), and a hold-off clamp (14). The hold-off clamp (14) is mounted independently…
The invention relates to a method of protecting an underwater conduit ( 100 ) against collapse, due to high hydrostatic pressures At least one bracing device ( 106 ) is applied around the external circumference of the conduit so as to define locally a region of increased wall…
A pipelaying vessel comprises storage ( 502 ) for a number of pipe units to be assembled into a pipeline and S-lay apparatus ( 312, 314, 316 ) for fabricating and paying out of a pipeline by repeated addition of new sections ( 506 ). The end of said pipeline being laid is held…
An apparatus for clamping friction pads to thin walled tubular structures of varying circumferences and taper angles is comprised of a frame which can be assembled around the tubular structure, one or more load arms for moving the one or more friction surfaces relative to the…
Described are structures, such as wind turbine structures for offshore sites, comprising transport elements configured for complementary mating with engagement elements of a clamp, which allow for transporting of the structures using that clamp. Generally, the transport element…
An apparatus to be mounted on a vessel for a laying a marine pipeline having accessories on the end of the pipeline and/or at one or more intermediate locations along the pipeline, said apparatus comprising a pipeline launch ramp ( 1 ) having pipeline guide means ( 6 ) for…
A fibre rope is used for hoisting articles from a vessel (12) in deep waters. The fibre rope has substantially neutral buoyancy. The rope (14) is handled in vertical orientation by a track type tensioner (18) or moving clamps, in order to avoid bend cycling under load.
An apparatus to be mounted on a vessel for a laying a marine pipeline having accessories on the end of the pipeline and/or at one or more intermediate locations along the pipeline, said apparatus comprising a pipeline launch ramp (1) having pipeline guide means (6) for guiding…
This invention relates to apparatus and methods for laying of elongate articles from a vessel. The vessel includes a tower ( 2 ), on which is supported tensioning means ( 20,21 ), straightening means ( 19 ), and a hold-off clamp ( 14 ). The hold-off clamp ( 14 ) is mounted…
A winching apparatus and method for winching a load are disclosed which are particularly suitable for, though not exclusively limited to, use with heave compensated hoists or cranes, for example, on a floating structure such as a vessel. The winching apparatus comprises a first…
Described are structures, such as wind turbine structures 100,1000 for offshore sites, comprising transport elements, eg an annular protrusion 150,250 configured for complementary mating with engagement portions 190 of a clamp 200,300 which allow for transporting of the…
330,173. Drew, W. S. July 23, 1929. Lantern screens.-In a colourchanging device for theatrical spotlights and other lamps in which a plurality of differently coloured screens are slidably mounted in a casing, the casing carries means which are externally operable from either…
Disclosed is an apparatus to be mounted on a vessel for laying a marine pipeline having accessories on the end of the pipeline and/or at one or more intermediate locations along the pipeline, the apparatus including a launch ramp having a guide for guiding and controlling the…