A method of erecting, and a method of servicing or dismantling, a wind energy plant with a hub height of at least 140 meters makes provision that a heavy-duty lifting device is temporarily disposed on a tower top for any installing, exchanging, or disassembling purposes, and…
Wagner Philipp
The invention relates to a tower construction for a wind turbine, said tower construction enabling very large hub heights due to a combination of inner prestress, guying, and a torsion-resistant tower shaft. The tower construction has a tower shaft, a foundation, and a…
A tower structure for a wind power plant which, at least in sections, is made of concrete and is stressed by carbon fibre tendons. This minimizes the construction effort.
A load-bearing structure and a method of producing a load-bearing structure, in particular a tower of a wind energy plant, provides a hollow concrete part with an outer wall which is manufactured by several layers produced in wet-on-wet technology. The outer layer is a…
A method of erecting, and a method of servicing or dismantling, a wind energy plant with a hub height of at least 140 meters makes provision that a heavy-duty lifting device is temporarily disposed on a tower top for any installing, exchanging, or disassembling purposes, and…
Die vorliegende Erfindung beschreibt einen Verbundquerschnitt für die Turmkonstruktion von Windenergieanlagen bestehend aus einem Betonverbund zwischen kohlefaserarmiertem Beton und Normalbeton. Erfindungsgemäß wird der Turmquerschnitt aus mehreren Betontypen entsprechend den…
The invention relates to preparations which are suitable for repairing enchondral or osteochondral defects (4) by means of implantation, said preparations comprising a cartilage element (A) and optionally a bone element (B) which is connected to the cartilage element (A). The…
A peak-flow monitor (10.1) comprises a body or tube (12) having an expiratory air inlet (18) and defining a flow path (14) for the expiratory air. A whistle (16) of the beating reed type is arranged in the flow path (14). The monitor (10.1) includes an annular wall (20) in which…
A pipe socket (18) surrounded by a flange (11) receives an end portion of a pipe piece (16). In an annular gap situated between them, a main sealing ring (12) of plastic, preferably Teflon, is arranged and an auxiliary seal having, for example, a radial shaft sealing ring (13)…
A gate valve for a vacuum chamber comprises two carriers ( 5 a ) each connected to a frame structure providing an essentially plane front by two parallel links ( 6 ) and to an actuating rod ( 12 a ) by parallel levers ( 14 ). Upward motion of the actuating rods ( 12 a ) by a…
A load-bearing structure and a method of producing a load-bearing structure, in particular a tower of a wind energy plant, provides a hollow concrete part with an outer wall which is manufactured by several layers produced in wet-on-wet technology. The outer layer is a…
Disclosed are wind farms with wind generators in several levels on top of each other. The wind generators are mounted on top of each other on towers. The towers are guyed using tendons. The tendons run crosswise between the towers. Additional safety tendons provide the wind farm…
The invention relates to a load-bearing structure and to a method for producing a load-bearing structure, in particular of wind turbine towers, which provides for a concrete hollow body having an outer wall which is produced by several wet in wet produced layers (22, 26). The…
Windenergieanlagen werden in immer größeren Dimensionen entwickelt, errichtet und betrieben. Ein elementares Manko großer Windenergieanlagen ist der wachsende technische Aufwand zur Errichtung immer größerer, schwererer Bauelemente in immer größeren Höhen. Es ist die Aufgabe der…
The tower structure comprises multiple nested tubes inserted into one another in a polygon shape. The tubes are interconnected by a web, whose cavities are filled with mass, where a frictional force exist between the tube elements and partly filled mass. The polygonal nested…
The hoist comprises tower shaft (1) attached with lift rail (2,7) and crane (3), such that the crane can be moved towards lift rail. The crane located on top of lift rail is extended to construction site at the head of tower shaft. An independent claim is included for wind…
Die Erfindung betrifft eine mobile Kranvorrichtung (10) zur temporären Montage an einem bestehenden Turmbauwerk (12) einer Windenergieanlage, mit einem Kranturm (14), der eine Längsachse (A) aufweist, welche in einem Montagezustand der Kranvorrichtung (10) am Turmbauwerk (12)…
The invention relates to a method for setting up and to a method for maintaining or disassembling a wind turbine having a hub height of at least 140 meters, wherein a heavy-duty lifting gear (54) is temporarily brought to the tower top (18) for installation, replacement or…
A method for setting up and maintaining or dismantling a wind energy installation having a hub height of at least 140m provides that for installation, replacement or dismantling a heavy-duty lifting device (54) is brought temporarily to the tower top (18) and then immediately…
The invention describes a wind power plant in which the positions of the wind generators overlap one another above in several planes. For this purpose, the wind generators are placed on top of each other on the tower structure. The tower construction is fixed by means of…
@ The invention discloses a string tensioning device (26) for use on a stringed racket. The device includes a string support member (38) adapted to be fitted to a string (52) on a racket which is to be tensioned; and an abutment member (28) cooperating with the string support…
The invention relates to preparations which are suitable for repairing enchondral or osteochondral defects ( 4 ) by means of implantation, said preparations comprising a cartilage element (A) and optionally a bone element (B) which is connected to the cartilage element (A). The…
A gate valve for a vacuum chamber comprises two carriers (5a) each connected to a frame structure providing an essentially plane front by two parallel links (6) and to an actuating rod (12a) by parallel levers (14). Upward motion of the actuating rods (12a) by a piston (17)…
The lifting unit has a tower structure, such that an outer side of the tower structure is moved freely up and down. A mounting platform (2) is integrated in the lifting unit. A tower shaft is trained for free movability of the lifting unit, such that the hoisting machine moves…