WO 0,136,753 A1#11076156 Most Cited · 9 citations0.4/yr · PR 3.29PendingWO · Application
Pile forming

A method of forming piles with a pile top level below ground level comprises the insertion of a casing into the ground so that the base of the casing is just below the desired pile top level, and the subsequent insertion of a continuous flight auger through the casing to form a…

WO 2004/081294 A1#33432158 Most Cited · 3 citations0.1/yr · PR 1.04PendingWO · Application
Method and apparatus for monitoring element alignment

The present invention relates to a method of measuring the difference in alignment between a first plan position of an element (1) and a second plan position of an element, the method comprising the use of: i) at least one rigid or taut connection (4) extending between a first…

WO 2005/071213 A1#44282684 Most Cited · 2 citations0.1/yr · PR 0.91PendingWO · Application
A casing for supporting a wall of a bore formed in the ground with watertighting joint section and method of making a secant pile wall using the segmental casing

The present applications relates to improvements in the joint used to couple together adjacent sections of a segmental casing (12) for supporting the wall of a bore formed in the ground. In order to reduce the required gap between complimentary portions (12, 13) of a two-part…

WO 0,102,651 A1#49412160 Most Cited · 1 citations0.0/yr · PR 0.89PendingWO · Application
Under-reamed diaphragm walls

A method of stabilising soil is disclosed comprising a diaphragm wall whose lower end is anchored in an under-reamed cavity filled with concrete, together with an under-reaming tool for constructing the cavity. The under-reaming tool comprises a hydraulically operated, circular…

WO 9,804,782 A1#48329253 Most Cited · 1 citations0.0/yr · PR 0.92PendingWO · Application
Improved stop-end system for use in diaphragm wall construction

There is disclosed a method and apparatus for removing a stop-end (1) from a concrete panel (5) during the construction of a diaphragm wall. An extractor tool (14) is provided with means (17) for attachment to the free face of the stop-end (1). The means (17) for attachment are…

WO 03,062,540 A1#121305928 Most Cited · 0 citations0.0/yr · PR 0.56PendingWO · Application
Construction and design of foundation elements

The present application relates to method of designing and forming a foundation element by consideration of a number of parameters including the contribution of ground material to the overall bearing capacity of the element. Techniques for analysing the load bearing capacity of…

WO 2004/081297 A1#138922920 Most Cited · 0 citations0.0/yr · PR 0.56PendingWO · Application
Placing elements in piles

The present application relates to an apparatus and method for placing an element (14), such as a steel column or concrete section, into a pile shaft (1) during top-down construction techniques. The apparatus is provided with an upper and lower positioning means (2, 3) which…

WO 9,851,867 A1#68019505 Most Cited · 0 citations0.0/yr · PR 0.56PendingWO · Application
Hydrophilic waterbar for diaphragm wall joints

A waterbar for use between adjacent panels (22, 24) in a diaphragm wall, the waterbar comprising a first member (5) in the form of an elongate strip (6) provided along a first longitudinal edge (8) with a hydrophilic material (7) and along the opposite longitudinal edge (9) with…