PROBLEM TO BE SOLVED: To improve accuracy when specifying a deterioration factor based on an image which images a concrete structure.SOLUTION: A concrete structure inspection support device comprises: an image reading part for reading image data in which a concrete structure as…
Maeda Construction
PURPOSE:To greatly increase strength of beam construction as well as contribution of lightweight beam construction, to prevent the cracks in concrete with the increase of load in the case the concrete is placed and to promote manufacture and construction efficiencies of a beam.…
To provide a construction support method for supporting efficient construction of a construction object using a three-dimensional model.SOLUTION: A construction support method comprises: a construction drawing acquiring step for acquiring a construction drawing; a construction…
PROBLEM TO BE SOLVED: To detect and identify a construction failure on the basis of the appearance of concrete after a form removal.SOLUTION: The construction quality evaluation program causes a computer to execute the following steps: an imaging step of imaging a concrete…
PROBLEM TO BE SOLVED: To provide an unmanned mechanical earth work system capable of carrying out civil engineering work of high accuracy such as a ground leveling or the like by complete unmanned operation in a disaster site or the like. SOLUTION: The unmanned mechanical earth…
PROBLEM TO BE SOLVED: To provide a method for appropriately managing construction work using several types of construction data accumulated through machine learning while executing structure construction work and maintenance inspection work.SOLUTION: In a structure construction…
To enable a work supervisor and workers to intuitively grasp a progress state by exactly grasping an actual construction state in a construction site of architecture and civil engineering.SOLUTION: A construction process management system includes: photographing means 10 for…
PROBLEM TO BE SOLVED: To provide a method for constructing a main tower made of concrete, to which a timbering girder can be reused, with the timbering girder being movable upward to a predetermined height without moving sideways. SOLUTION: A bracket 11, a timbering girder 13,…
PURPOSE:To permit concurrent performance of consolidation test and water permeation test by a method in which the soil sample is measured by using a pressure rod with a displacement meter and at the same time displacement is measured by introducing water discharged through the…
The present invention relates to an openable roof having two pairs of half dome openable roofs provided on a ring shaped set roof having a flat upper surface. In the center of the set roof, an aperture is provided; this aperture being opened or closed by these two pairs of…
PROBLEM TO BE SOLVED: To provide an earth retaining method of an excavation section capable of being executed even at a comparatively narrow space, at the same time, increasing efficiency of excavation work and skeleton construction work of a building even if the building is…
PROBLEM TO BE SOLVED: To evaluate the workability on the basis of an image of a test piece in a slump test.SOLUTION: The workability evaluation program causes a computer to execute the following steps: an imaging step of imaging a test piece of a ready-mixed concrete molded with…
<P>PROBLEM TO BE SOLVED: To provide a method and a device for controlling a banking rolling, by which the ground rigidity of all surfaces can be measured automatically in parallel with rolling works. <P>SOLUTION: In a self-propelled roller car 1, in which a roller 4…
<P>PROBLEM TO BE SOLVED: To enable a macroscopic bore displacement of a tunnel cross section to be always obtained with a measurement accuracy that is fully practically, and to enable a maintenance-free structure to be realized by using a simple mechanism.…
To support a structure design satisfying a predetermined standard for a cross section of a building member.SOLUTION: A design support apparatus includes: a model generation unit for reading from a storage device a three-dimensional building model indicating an arrangement of…
PROBLEM TO BE SOLVED: To reuse a timbering girder to a another usage and to move the timbering girder upward to a predetermined part without moving it sideways. SOLUTION: A bracket 13, a timbering girder 15, a form 17, and the like which are used in the construction of a…
The present invention relates to an openable roof having two pairs of half dome openable roofs provided on a ring shaped set roof having a flat upper surface. In the center of the set roof, an aperture is provided; this aperture being opened or closed by these two pairs of…
Provided is a technique that enables a pozzolan admixture to be universally obtained from a variety of raw materials. The pozzolan admixture is formed from feedstock containing coal gangue. The feedstock contains at least SiO 2 , Al 2 O 3 , CaO and SO 3 . The SiO 2 , Al 2 O 3…
A method for detecting a leakage position in an impervious sheet, which comprises disposing a first and a second electrode units on an upper side and a lower side of the impervious sheet, respectively, the first electrode unit intersecting with the second electrode unit;…
A method of easily consecutively manufacturing a layered structure with the same or different kinds of materials superposed in a plurality of layers, is attained by a simple mechanical method. The layered structure manufacturing method is embodied by use of a shaping apparatus…
PROBLEM TO BE SOLVED: To provide a material lifting device capable of lifting a variety of materials while keeping them in a predetermined attitude, and capable of directly conveying the lifted material to a desired site without bringing a crane into contact with, if any, an…
<P>PROBLEM TO BE SOLVED: To solve the problem that formation of an arrival hole is required by breaking a shaft wall face and spring water or the like arises when the wall face is broken in order to install the arrival part when a shield machine arrives at an arrival…
<P>PROBLEM TO BE SOLVED: To provide a tunnel support erection method and a tunnel support erection system of excellent accuracy, work efficiency, economical efficiency and safety allowing the adjustment of an installed position of the tunnel support while always monitoring…
<P>PROBLEM TO BE SOLVED: To appropriately sprinkle water to maintain the surface of concrete in a suitable wet state for sprinkling water on the placed surface for curing concrete after placed. <P>SOLUTION: This wet curing apparatus 2 for concrete includes a track 3…
<P>PROBLEM TO BE SOLVED: To construct safely and easily a bridge pier by using a concrete columnar structure whose crack dispersion and rigidity can be greatly improved and shorten the construction term. <P>SOLUTION: In the construction method of a bridge pier using…