A method of transporting rails to, and leaving the rails at, a target location. The method includes using a train having multiple rail wagons. The steps include supporting the rails on at least two successive wagons with the rail being movable relative to at least one wagon in…
Fastline Ltd
A method of transporting rails to, and leaving the rails at, a target location. The method includes using a train having multiple rail wagons. The steps include supporting the rails on at least two successive wagons with the rail being movable relative to at least one wagon in…
A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the…
A rail wagon (100, 400, 500, 700) is disclosed for the deployment of a panel of track or sleeper set from the wagon to an adjacent substantially parallel track bed in a single laying operation. Each wagon comprises a crane hoist (102, 403, 504) moveable from a transit position…
Rails 11 are supported by a succession of wagons 200 by rollers 307. Crane hoists 202 lift the rails on to and off the wagons. Stacks of sleepers 12 are also lifted on to and off the wagons 200 by the hoists 202.
Rotors 8 are driven by motors in housings 20 to direct ballast on an apron 6. The motors and rotors can be raised from the apron 6 to allow for repair or replacement of any of these components.
A storage unit (100, 200) for storage of stacked railway sleepers is disclosed. Each unit comprises a base portion (101, 201) comprising apertures defining channels configured to receive the fork of a forklift vehicle to facilitate manipulation and lifting of the unit (100,…
A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the…
A method and apparatus are disclosed for protecting users who must access a potentially dangerous location. By having users wishing to access that location first identify themselves and identify that they are trained to enter that location and to thereafter be allocated a access…
The apparatus comprises a movable apron 6 with rotors 8 driven by motors in housings 20 to direct ballast on the apron 6. The motors and rotors can be raised from the apron 6 to allow for repair or replacement of any of these components. The motor housings 20 are above the…
A rail wagon ( 100, 400, 500, 700 ) is disclosed for the deployment of a panel of track or sleeper set from the wagon to an adjacent substantially parallel track bed in a single laying operation. Each wagon comprises a crane hoist ( 102, 403, 504 ) moveable from a transit…
A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the…
A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the…
A rail wagon (100, 400, 500, 700) is disclosed for the deployment of a panel of track or sleeper set from the wagon to an adjacent substantially parallel track bed in a single laying operation. Each wagon comprises a crane hoist (102, 403, 504) moveable from a transit position…
A method and apparatus are disclosed for protecting users who must access a potentially dangerous location. By having users wishing to access that location first identify themselves and identify that they are trained to enter that location and to thereafter be allocated a access…
Rails 11 are supported by a succession of wagons 200 by rollers 307. Crane hoists 202 lift the rails on to and off the wagons. Stacks of sleepers 12 are also lifted on to and off the wagons 200 by the hoists 202.
A continuous method of removing ballast material particularly from a railway line bed comprising the steps of positioning an excavation apparatus (1) at the work site, advancing the apparatus along the bed to lift ballast from the bed, introducing the lifted ballast into the…