A method for installing rig structure (e.g. cabin, house, a doghouse) on a drilling rig, the method including: connecting support apparatus to a substructure of a drilling rig, supporting a drilling floor; moving a movement apparatus supporting a rig structure to position it…
Donnally Robert Benjamin
Methods for connection parts of a mast of a drilling rig without using a crane or other lifting machine are disclosed. In certain aspects, these methods include moving parts of a mast to be assembled with trucks and positioning the parts with the trucks to facilitate their…
A method for installing rig structure (e.g. cabin, house, a doghouse) on a drilling rig, the method including: connecting support apparatus to a substructure of a drilling rig, supporting a drilling floor; moving a movement apparatus supporting a rig structure to position it…
Systems and methods for erecting a drilling rig. This abstract is provided to comply with the rules requiring an abstract which will allow a searcher or other reader to quickly ascertain the subject matter of the technical disclosure and is submitted with the understanding that…
Methods for connection parts of a mast of a drilling rig without using a crane or other lifting machine are disclosed. In certain aspects, these methods include moving parts of a mast to be assembled with trucks and positioning the parts with the trucks to facilitate their…
Systems and methods for erecting a drilling rig. This abstract is provided to comply with the rules requiring an abstract which will allow a searcher or other reader to quickly ascertain the subject matter of the technical disclosure and is submitted with the understanding that…
Methods and systems for installing a drawworks on a drilling rig, the method, in certain aspects, including moving a drawworks on movement apparatus on the ground adjacent a drill floor of a rig, connecting the drawworks to the drill floor, moving the movement apparatus away…
A system for erecting a drilling rig mast includes a substructure having an open area that is defined therein by two laterally spaced-apart substructure sides and a first mast section that is adapted to be positioned at least partially within the open area of the substructure…
A method for facilitating assembly and erection of a drilling rig, the drilling rig comprising a structure (11,12) and a mast (20,30), the mast (20,30) comprising at least a first mast section (20,120) and a second mast section (30,130), the method comprising the steps of…
A method for facilitating construction of a drilling rig, the method comprising the steps of moving a drawworks (10) on movement apparatus (T,R ) along ground (G) adjacent a drill floor (28 ) of a drilling rig structure (20), the drilling rig structure (20) having a substructure…
A pipe handling system including a lifting system for handling a load of a pipe stand, a pipe handling robot (116a, 116b) configured for engaging with the pipe stand (110) and manipulating a position of the pipe stand (110), and a feedback device configured to provide…
A system for erecting a drilling rig mast includes a substructure having an open area that is defined therein by two laterally spaced-apart substructure sides and a first mast section that is adapted to be positioned at least partially within the open area of the substructure…
Systems and methods for rig assembly and for erecting a mast of a rig and such systems with roller apparatus to facilitate movement of a mast section from a mover. In a first embodiment, the method includes erecting a rig mast section on a substructure, the substructure…
Systems and methods for clearing a top drive (118) from an operational area of the mast such that operations may be performed along a top drive guide rail (120) without interference from the top drive (118). The guide rail (120) may be arranged within an operational area of a…
A method and system for facilitating assembl y of a dr illing rig, the method comprising the steps of assembling a substructure (20) of a drilling rig, wherein the substructure compris es a lower structure (14) arranged on the ground and an upper structure (12) arranged…
Disclosed herein is a bi-directionally raisable drilling rig mast system that includes a drilling rig mast (530) having a bi-directional mast erection connection (534), a first erection connection (507f) positioned proximate a first side (600f) of a rig substructure (500), and a…
Disclosed herein is a raisable substructure (100) of a drilling rig (200) that includes first and second substructure boxes (101, 102). The first and second substructure boxes (101, 102) of the raisable substructure (100) each include, among other things an upper box (101u,…
A method for facilitating assembly and erection of a drilling rig, the drilling rig comprising a drill floor (12,112) and a substructure (16,116), the method comprising the steps of positioning a rig structure (17,40,140) adjacent the drill floor (12,112) with a vehicle (T),…
Method for assembling and erecting a drilling rig without the use of a crane or the drawworks. The drill floor (12) is mounted on a substructure (16) and can be raised to its operating position by telescoping arm (16a). Two suspending arms (22) are secured to the drill floor. A…
A method for facilitating construction of a drilling rig, the method comprising the steps of moving a drawworks (10) on movement apparatus (T,R ) along ground (G) adjacent a drill floor (28 ) of a drilling rig structure (20), the drilling rig structure (20) having a substructure…
A method and system for facilitating assembl y of a dr illing rig, the method comprising the steps of assembling a substructure (20) of a drilling rig, wherein the substructure compris es a lower structure (14) arranged on the ground and an upper structure (12) arranged…
Disclosed herein is a raisable substructure (100) of a drilling rig (200) that includes first and second substructure boxes (101, 102). The first and second substructure boxes (101, 102) of the raisable substructure (100) each include, among other things an upper box (101u,…
Disclosed herein is a bi-directionally raisable drilling rig mast system that includes a drilling rig mast (530) having a bi-directional mast erection connection (534), a first erection connection (507f) positioned proximate a first side (600f) of a rig substructure (500), and a…
A pipe handling system may include a travelling block (128) configured for raising and lowering a drill string arranged at well center (138) and for travelling along the drill string. The pipe handling system may also include a primary elevator (132) operably coupled to the…
A drilling rig having a lift arm, which may be an auxiliary lift arm provided in addition to a primary lifting cable system of the drilling rig. The lift arm may be configured to hoist and/or manipulate drill collar, drill pipe, or other drilling pipe or conduit. The lift arm…