KR 101,011,322 B1#4378263 Most Cited · 19 citations1.3/yr · PR 8.61ActiveKR · Utility
Tip open pile having reinforcing apparatus for buried pile
Inventors: Choi Dong Sub, Min Byeong ChanAssignee: Choi Dong Sub, Shinsegae Engineering & Contruction LtdFiled 2010-03-23 · Granted 2011-01-28

PURPOSE: A hollow open-ended pile for embedded piles with an end reinforcement device having a penetration steel pipe for penetration is provided to effectively prevent longitudinal cracking of the leading end of a pile. CONSTITUTION: A hollow open-ended pile for embedded piles…

KR 20090080795 A#12381684 Most Cited · 8 citations0.5/yr · PR 4.88ActiveKR · Utility
PHC pile having reinforcing shoe adhered to end
Inventors: Choi Dong SubAssignee: Choi Dong Sub, Shinsegae Engineering & ContruFiled 2008-01-22

A PHC pile having a leading end reinforcement shoe is provided to minimize the influence of slime, to decrease the degree of subsidence by driving into a stable bearing layer, and to increase the bearing capacity for a leading end by increasing the area of a leading end. A PHC…

KR 20130037283 A#13414491 Most Cited · 8 citations0.6/yr · PR 1.82ActiveKR · Utility
Tensioning air beam system with curved type lcwer member and upper member
Inventors: Kim Jong Soo, Baek Ki YoulAssignee: Cs Structural Engineering Inc, DongastFiled 2011-10-06

PURPOSE: A tensioning air beam system with curved type lower and upper chord members is provided to be effective to a continuous beam by delivering tensile force caused by a cable to upper and lower steel materials, and to strengthen resistance properties against bending moment.…

KR 100,912,574 B1#16685333 Most Cited · 6 citations0.3/yr · PR 2.20ActiveKR · Utility
Retaining wall system using strut assembly and excavating method using the same
Inventors: Choi Dong SubAssignee: Cs Structural Engineering Inc, Shinsegae Engineering & ContruFiled 2008-04-25 · Granted 2009-08-19

A retaining wall system using a prefabricated strut assembly and an excavation method using the system are provided to carry out excavation continuously and rapidly as the struts bear the soil pressure while supporting the load of concrete slab. A retaining wall system using a…

KR 20090093579 A#20515233 Most Cited · 5 citations0.3/yr · PR 1.56ActiveKR · Utility
Connecting structure for form-less column and deck beams, and constructing method thereof

A joint structure between a form-less column and a deck beam and a construction method thereof are provided to shorten the construction period and to cut down on the construction cost because the integrity of the joint between a form-less column and a deck beam is intensified…

KR 20090126626 A#19732110 Most Cited · 5 citations0.3/yr · PR 1.85ActiveKR · Utility
Membrane tension measurement device
Inventors: Jung Hwan MokAssignee: Cs Structural Engineering Inc, Tiger CorpFiled 2008-06-04

PURPOSE: A film tension measurement device is provided to carry conveniently and detect a biaxial tension of the installed film structure. CONSTITUTION: A film tension measurement device comprises a detection member(20), and a welded joint jig(30) and a fixing unit(40). The…

KR 20100002643 A#20742294 Most Cited · 5 citations0.3/yr · PR 1.51ActiveKR · Utility
Temporary construction system for the automation of building projects and construction method using the same

PURPOSE: A temporary construction system of automatic construction and an automatic construction method using the same are provided to position a working robot on every corner of constructed parts by simplifying the whole structure. CONSTITUTION: A temporary construction system…

KR 20090114956 A#31416375 Most Cited · 3 citations0.2/yr · PR 1.15ActiveKR · Utility
A bolt for assembly and space frame having this

PURPOSE: A bolt for assembly and a space frame with the same is provided to prevent a pin connection part and a through part from breaking out by external force and to increase durability of the space frame. CONSTITUTION: A space frame with a bolt for assembly comprises a body…

KR 20100130376 A#32137338 Most Cited · 3 citations0.2/yr · PR 1.12ActiveKR · Utility
Temporary construction frame system for the automation of building projects

PURPOSE: A prefabricated temporary installation support frame for an automation construction, which has a trussed structure for structural stability and lightness, is provided to reduce installation costs and to improve structural stability and lightness. CONSTITUTION: A…

KR 20100123538 A#36668644 Most Cited · 2 citations0.1/yr · PR 1.15ActiveKR · Utility
Lift up building method of roof structure
Inventors: Jung Hwan MokAssignee: Jung Hwan Mok, Cs Structural Engineering IncFiled 2009-05-15

PURPOSE: A method for automating the installation of the roof structure of a large-span building is provided to prevent the falling of a worker because a roof structure is completed on the ground and lifted up to be installed. CONSTITUTION: A method for automating the…

KR 101,163,583 B1#50904212 Most Cited · 1 citations0.1/yr · PR 0.85ActiveKR · Utility
Initial cable tensioning guide and initial cable tensioning system having this and initial cable tensioning method using this
Inventors: Kim Sung BumAssignee: Korea Construction Quality Res Ct, Jang Woo SeogFiled 2011-08-18 · Granted 2012-07-09

PURPOSE: An initial tension system of a cable having an initial tension guide and an initial tension method of a cable using the same are provided to easily set an initial relative position between a cable and a tension control device even if the distance from the tension…

KR 20100114641 A#50240710 Most Cited · 1 citations0.1/yr · PR 0.86ActiveKR · Utility
Tensioning air beam system
Inventors: Kim Jong Soo, Baek Ki YoulAssignee: Cs Structural Engineering IncFiled 2009-04-16

PURPOSE: A tensioning air beam system, which can be usefully utilized for structure construction, is provided to increase the structural strength of cable and to reduce the weight of an air tube. CONSTITUTION: A long-span tensioning air beam system comprises a steel member(10),…

KR 20100114642 A#57716876 Most Cited · 1 citations0.1/yr · PR 0.79ActiveKR · Utility
Tensioning air beam system with a long span
Inventors: Baek Ki Youl, Kim Jong SooAssignee: Cs Structural Engineering IncFiled 2009-04-16

PURPOSE: A long-span tensioning air beam system can be usefully utilized for structure construction by increasing load bearing force is provided to increase the structural strength by the tension of a cable. CONSTITUTION: A long-span tensioning air beam system comprises a steel…

KR 20110116298 A#53729500 Most Cited · 1 citations0.1/yr · PR 0.82ActiveKR · Utility
Rotating-up building roof structure using keel truss and rotating-up building method using keel truss

본 발명은 대공간 구조물 가설장치 및 가설방법에 관한 것으로, 바닥에 기초부재를 연속적 또는 비연속적으로 가설하는 가설준비단계, 반대방향으로 뉘어진 한 쌍의 킬트러스 각각의 양측을 대응되는 기초부재에 힌지 연결하는 킬트러스 장착단계, 이 킬트러스에 서로 교차되게 각각 묶여진 로프부재를 기초부재 또는 바닥에 형성된 회전릴부재에 감는 킬트러스 가설준비단계, 이 회전릴부재 각각을 강제 회전시킴으로써 로프부재를 통해 킬트러스 각각을 세우는 킬트러스 스탠딩단계, 및 이 킬트러스 각각을 기초부재 또는…

KR 101,073,470 B1#79787200 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
Tensioning air beam system with lower member and upper member
Inventors: Kim Jong Soo, Baek Ki YoulAssignee: Cs Structural Engineering IncFiled 2010-04-19 · Granted 2011-10-17

본 발명은 강재와 에어튜브를 케이블로 결합하여 구조내력과 경량성에서 유리하게 완성한 텐셔닝 에어빔 시스템에 관한 것으로, 더욱 상세하게는 강재를 에어튜브 상·하부에 배치하여 케이블로 결합함으로써 압축측과 인장측의 하중에 유리하게 저항할 수 있도록 구성한 텐셔닝 에어빔 시스템에 관한 것이다. 본 발명에 따른 텐셔닝 에어빔 시스템은, 길이방향으로 긴 강재에 의한 상현재; 상기 상현재 아래에 이격 배치되는 길이방향으로 긴 강재에 의한 하현재; 내부에 공기가 채워지는 길이방향으로 긴 부재로 상기…

KR 20090114088 A#139180438 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
System and Method for measuring indoor sound

PURPOSE: A system and a method for measuring an indoor sound are provided to analyze spread sound field by quantifying sound dispreading degree at any space. CONSTITUTION: In a system and a method for measuring an indoor sound, a microphone(100) receives an audio signal. A…

KR 20110106528 A#98919535 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
Tip open pile having reinforcing apparatus for buried pile

본 발명은 매입말뚝공법으로 시공되는 중공형 개단말뚝에 관한 것으로, 보다 상세하게는 말뚝 선단의 응력분산이 뛰어나 선단지지력을 향상시킬 수 있고 선단고정액과의 합성효과로 보다 우수한 선단폐색효과를 기대할 수 있으며 선단폐색으로 인한 말뚝 선단의 종방향 균열을 효과적으로 방지할 수 있는 선단보강장치를 구비한 중공형 개단말뚝에 관한 것이다. 본 발명의 적절한 실시 형태에 따르면, 내부에 중공이 형성되고 선단이 개방된 중공형 개단말뚝을 매입말뚝에 적용하기 위해 선단에 선단보강장치가 결합되며,…

KR 20130015861 A#95206628 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
Falling prevention system of moving rail on construction factory for auto-construction

PURPOSE: The fall prevention device of a horizontal movement rail in a construction factory of an automation architecture system is provided to absorb a micrometric displacement according to up and down movement of the construction factory or a vibration, to comprise a…

KR 20150112139 A#89123971 Most Cited · 0 citations0.0/yr · PR 0.56ActiveKR · Utility
The pre-stressed composit beam structure

The present invention relates to an eco-friendly pre-stress composite beam structure and, more specifically, to an eco-friendly pre-stress composite beam structure which has an excellent performance by using a strand in a composite beam formed of an iron plate, supports…