Method to start up a combined cycle thermal plant for energy production from an off-state to an operational state
Abstract
To start a combined cycle thermal plant for energy-production from an off-state to an operational state, once the minimum warm-up time of the steam turbine (ST) having been set, as well as the pressure of the warm-up steam, it is necessary to determine the steam optimum temperature to avoid stressing or straining the mechanical parts of the turbine itself.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 9 · Forward citations: 0.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A method to minimize time for the start up of a combined cycle thermal plant for energy production from an off-state to an operational state, said combined cycle thermal plant for energy production comprising a first gas turbine and generator group (TGI), a first recovery steam generator (GRV 1 ) to regenerate latent heat of exhaust gases of said first gas turbine and generator group (TGI), a steam turbine (TV), a generator coupled to said steam turbine (TV), and a nozzle/steam distributor, wherein: said first recovery steam generator (GRV 1 ) is in fluid communication with said steam turbine
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (0 of 0 total)
No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.
References Cited — Backward Prior Art (9)
Non-Patent Literature (1)
- International Search Report for PCT/IB2012/051450, mailed Jun. 20, 2012, 3 pages.