Abstract

A process of implementing, or engineering, topology-dependent functions based on a formal description of the Substation Automation system, includes performing a topology analysis of the current single line state. A topology interpreting implementation replacing complex topology analysis logics can include the project specific static single line topology and the connection to the real process state data. All information can be delivered in an IEC 61850 conforming SCD file. The interface description for controlling and monitoring the load transfer application can be generated automatically from the SCD file.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 9 · Forward citations: 2.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method of implementing a load transfer function in a Substation Automation SA system for a substation supplying electric power to a load, comprising: reading a standardized configuration description of the SA system, to obtain a static topology representative of at least a part of the substation as well as information about primary elements of the substation; repeatedly updating a dynamic substation topology based on a switch status of a switching device of the substation; for a transformer connecting a first bus bar to a second bus bar of the substation, identifying, based on the dynamic su

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (1)

  • European Search Report for EP 10167226 dated Oct. 18, 2010.