Crane and method for erecting the crane
Abstract
A method for telescoping a main boom includes guying the erected main boom during the telescoping operation, the main boom consisting of a telescopic boom which is guyed via a spatial boom guying. Further, a crane may include a telescopable main boom, a spatial guying and a crane controller, wherein the crane controller determines the necessary guy dimension of the spatial guying in dependence on the current main boom length during the telescoping operation.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 9 · Forward citations: 3.
Claims (3 — 1 Independent, 2 Dependent)
- Claim 1Independent Claim
A method for telescoping a main boom including a telescopic boom, which is guyed via a spatial boom guying, the method comprising: limiting the main boom in its lateral deflection when erected by tensioning the spatial guying during telescoping operation to ensure a sufficient guying force into the telescopic boom.
- Claim 2Depends on #1
The method according to claim 1 , wherein the main boom is guyed during the telescoping operation, and where in a retracted condition the telescopic boom is guyed by the spatial guying, and wherein during the telescoping operation a dimension of the spatial guying is varied synchronously with the telescoping of the boom.
- Claim 3Depends on #2
The method according to claim 2 , wherein the synchronization between the telescoping operation and the variation of the spatial guying is executed by a crane control
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (3 of 3 total)
References Cited — Backward Prior Art (9)
Non-Patent Literature (1)
- ISA German Patent and Trademark Office, Search Report of DE 10 2010 020 016.6-22, Apr. 27, 2011, 2 pages.