Abstract

A computer implemented method and computer system for management of materials on a construction site. In one embodiment, at least one cost scenario is defined for moving at least one material with a vehicle pool. A status of a project which uses the material is then determined. A report is generated which identifies a vehicle of the vehicle pool and defines a load of the material which is to be moved by the vehicle from a first location to a second location.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 8 · Forward citations: 15.

Claims (2 — 1 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    A computer implemented method for management of materials on a construction site, said method comprising: defining at least one cost scenario to move at least one material with at least one vehicle from a vehicle pool; determining a status of a project which uses the at least one material; generating a report which identifies a vehicle from said vehicle pool to be utilized and defines a load of the material which is to be moved by said vehicle, according to a mass haul plan, from a first location which is a cut section to a second location which is a fill section; automatically updating the st

  2. Claim 2Depends on #1

    The method as recited in claim 1 wherein said defining fur