Abstract
A system for protecting, controlling, and monitoring substation devices of a power system, includes a spare protection and control unit that, when there is a failure in a protection and control unit from among protection and control units that perform a protection and control operation for the substation devices, downloads unit information including software and a device setting value of failed protection and control unit from a database unit and functions as an alternative unit for the failed protection and control unit.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 14 · Forward citations: 8.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A system for protecting, controlling, and monitoring substation devices of a power system, the system comprising: a plurality of protection and control units that are connected to a first bus and a second bus and perform a protection and control operation for the substation devices; a database unit that is connected to the second bus and stores therein unit information that includes software and a device setting value for each of the protection and control units; a spare protection and control unit that is connected to the first bus and the second bus, and when there is a failure in a protecti
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (8 of 8 total)
References Cited — Backward Prior Art (14)
Non-Patent Literature (5)
- Apostolov et al, "Impact of IEC 61850 on Power System Protection", Oct. 29, 2006, IEEE, pp. 1053-1058.
- Baigent et al, "IEC 61850 Communication Networks and Systems in Substations: An Overview for Users", Nov. 10, 2004, SISCO, pp. 36.
- Combined Search and Examination Report issued in corresponding United Kingdom Application No. 0909823.7 dated Oct. 6, 2009.
- Lee et al, Fault tolerant Technology to increase Reliability for IEC 61850 based Subsattion Automation System, 2006, CIGRE.org, pp. 9.
- Rim et al, "Multi-agent based reliability Enhancement Scheme for IEC61850 Substation", Apr. 2008, IEEE, pp. 1-6.