Patents
US 8,105,823 B2#31466425 Most CitedActiveUnited States (USPTO)Utility

Biogas installation for production of biogas from biomass, and methods for operation of the biogas installation

3Forward Citations (#31466425 Global)
0.2/yrCitation Velocity (#32396107 Global)
1.15Citation PageRank (#34206206 Global)
18Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

A biogas installation for production of biogas from biomass and methods for starting and shutting down a fermenter are disclosed. When biomass in a fermenter is used up, biogas production must stop, the fermented biomass removed, and the fermenter filled with fresh biomass. Biogas production and utilization is maintained for as long as possible. When the methane concentration in the biogas outlet falls below an upper limit, the biogas line is disconnected. The biogas/off-gas mixture is fed out via an exhaust chimney until the methane concentration has fallen to a lower limit. The fermenter to be shut down is purged with fresh air, and the off-gas/biogas/fresh air mixture is fed out via the exhaust chimney until the carbon-dioxide concentration in the off-gas/biogas/fresh air mixture has fallen to a first limit. The fermenter is then opened to unload the consumed biomass and load fresh biomass.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 18 · Forward citations: 3.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    Method for shutting down a fermenter in a biogas installation, the biogas installation comprising the fermenter which operates on the principle of dry fermentation for production of biogas in the batch mode with a biogas outlet and a purging gas inlet; a biogas line connected to the biogas outlet, an off-gas line by means of which off-gas containing carbon dioxide is supplied to the purging gas inlet, an off-gas chimney connected to the biogas outlet via a first biogas/off-gas line, an off-gas flare connected via a second biogas/off-gas line to the biogas outlet, a fresh air line connected to

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

References Cited — Backward Prior Art (18)

PatentTitleYearCitations
DE 3,438,057 A1Process for the treatment of biomasses—17
SU 1,748,693 A1Installation for processing of organic waste of animal breeding and plant growing into biological gas and materials for production of fertilizers19925
DE 19,719,323 A1Batch tunnel fermentation of biowastes comprises combining aerobic and anaerobic treatments—41
EP 0,934,998 A2Method and device for the methanation of biomasses—48
WO 0,206,439 A2Bioreactor for methanising biomass and a biogas installation for producing thermal, electric or mechanical energy from biomass using said bioreactor, method for regulating and controlling one such biogas installation—61
EP 1,301,583 A2Bioreactor for methanising biomass and a biogas installation for producing thermal, electric or mechanical energy from biomass using said bioreactor, method for regulating and controlling one such biogas installation—6
EP 1,354,940 A2Process and apparatus for conversion of biodegradable organic materials into product gas—28
DE 20,319,847 U1Large scale fermenter, to produce a biogas from a relatively dry biomass, has a vertical framework on the base plate to support a gas-tight film shrouding with a sealed loading/unloading opening—20
RU 2,254,700 C1Biogas apparatus for anaerobic fermentation of organic wastes20059
US 6,969,562 B2Fuel cell power generation method and system200518
US 2006111575 A1Non-routine reactor shutdown method—24
EP 1,681,274 A2Method and device for carrying out a fermentation process in a reactor.—29
US 2006223154 A1Method and bioreactor for producing synfuel from carbonaceous material—30
EP 1,762,607 A1Control method for biogas installations—54
EP 1,997,875 A1Biogas facility for creating biogas from biomass and method for operating the biogas facility—28
US 2008299634 A1Biogas Installation for Production of Biogas from Biomass, and Methods for Operation of the Biogas Installation—13
US 7,481,940 B2Biomass treatment of organic waste or water waste200921
US 2009239209 A1Combined installation for the production of biogas and compost, and method of switching a fermenter in a like installation between biogas production and composting—15

Non-Patent Literature (3)

  • English translation of Lutz (WO 02/06439).
  • Eurasian Search Report mailed Jul. 1, 2009, for EA Application No. 2420-158974, two pages.
  • Search Report for Eurasian Patent Application No. 200801217, dated Oct. 13, 2008.