Staged deployment for electrical charge spots
Abstract
A method and system is provided to deploy electrical charge spots in stages according to demand. During a first stage a plurality of infrastructure adapters are installed. This may involve demolishing and rebuilding portions of the infrastructure and laying down power cables from the electrical power supply to the charge spot locations. The infrastructure adapters are then coupled to an electrical power supply. Many if not all of the infrastructure adapters are covered with a temporary housing protecting them from vandalism and weather. During a second stage, in response to a demand for charge stations, the charge stations are completed. During the second stage, at least one external unit is attached to an infrastructure adapter by making an infrastructure adapter quick connect interface with an external unit quick connect interface. As such, a charge spot is completed quickly in response to demand.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 50 · Forward citations: 11.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A method of staged deployment of an electrical charge spot system for charging at least partially electric vehicles, comprising: during a first stage: installing one or more infrastructure adapters, each infrastructure adapter comprising a power supply electrical interface and an adapter quick connect interface; coupling the power supply electrical interface of the infrastructure adapter to a power supply; during a second stage: installing one or more external units, each external unit comprising a car electrical connector, configured to temporarily electrically connect to and charge an at lea
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗