Patents
US 8,028,151 B2#44265419 Most CitedActiveUnited States (USPTO)Utility

Performance of an in-order processor by no longer requiring a uniform completion point across different execution pipelines

2Forward Citations (#44265419 Global)
0.1/yrCitation Velocity (#41875158 Global)
0.91Citation PageRank (#47162544 Global)
12Prior Art Cited
2Claims (1 Indep. · 1 Dep.)
0Drawings / Sheets

Abstract

A method, system and processor for improving the performance of an in-order processor. A processor may include an execution unit with an execution pipeline that includes a backup pipeline and a regular pipeline. The backup pipeline may store a copy of the instructions issued to the regular pipeline. The execution pipeline may include logic for allowing instructions to flow from the backup pipeline to the regular pipeline following the flushing of the instructions younger than the exception detected in the regular pipeline. By maintaining a backup copy of the instructions issued to the regular pipeline, instructions may not need to be flushed from separate execution pipelines and re-fetched. As a result, one may complete the results of the execution units to the architected state out of order thereby allowing the completion point to vary among the different execution pipelines.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 12 · Forward citations: 2.

Claims (2 — 1 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    A method for improving the performance of an in-order processor comprising the steps of: detecting an exception at or before a completion point for an execution pipeline, wherein said execution pipeline comprises a backup pipeline and a regular pipeline, wherein said backup pipeline stores a copy of instructions issued to said regular pipeline; asserting an upper stall point to prevent instructions from entering said backup pipeline and said regular pipeline; asserting a lower stall point to prevent instructions from flowing out of said backup pipeline; flushing instructions younger than an in

  2. Claim 2Depends on #1

    The method as recited in claim 1 further comprising the step of: de-asserting s

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (2)

  • "Combination of Forwarding/Bypass Network with History File," IBM, U.S. Appl. No. 11/095,908, filing date Mar. 31, 2005, pp. 1-30.
  • Barnes, R. D., Nystrom, E. M., Sias, J. W. "Beating in-order stalls with "flea-flicker" two-pass pipelining" 36th International Symposium on Microarchitecture, Dec. 3-5, 2003, p. 387-98.