System and process for job scheduling to minimize construction costs
Abstract
Increased efficiency and lower cost job scheduling is provided by a system and method that optimizes for cost instead of makespan, and minimizes fluctuations in resource utilization. A schedule is constructed using a workflow scheduling system that includes a load leveler, a cost minimizer, and a manpower planner. The load leveler minimizes makespan, subject to resource limits, and then lowers the resource limits, repeating the process in order to create a flatter schedule. The cost minimizer generates an initial solution, and then incrementally improves it, using the manpower planner to evaluate the different possible solutions. The manpower planner calculates, for a given schedule, the optimal hire/fire decisions to minimize total cost.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 13 · Forward citations: 11.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A scheduling system for generating a schedule of start times for a plurality of tasks for a project, at least one task of the plurality of tasks having associated resources utilized to perform the task, the system comprising: at least one processor; a load leveler subsystem, executed by at least one of the processors, configured to receive data representative of the plurality of tasks for the project, and to generate a proposed schedule of start times for the plurality of tasks responsive to at least one scheduling constraint between at least two of the plurality of tasks and fluctuations of r
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (11 of 11 total)
References Cited — Backward Prior Art (13)
Non-Patent Literature (5)
- "A Heuristic Model for Scheduling Large Projects with Limited Resources" Jerome D Wiest Management Science, vol. 13, No. 6, Series B, Managerial (Feb. 1967).
- (Amico) Dell'Amico, M. and Trubian, M. 1993. Applying tabu search to the job-shop scheduling problem. Ann. Oper. Res. 41, 1-4 (May 1993), 231-252.
- (Smith) A. Cesta, A. Oddi, and Stephen Smith, "Iterative Flattening: A Scalable Method for Solving Multi-Capacity Scheduling Problems," Proceedings National Conference on Artificial Intelligence (AAAI-00), Jul. 2000.
- (Stidsen) T. Stidsen, L. V. Kragelund, O. Mateescu, Jobshop Scheduling in a Shipyard, European Conference on Artificial Intelligence, Budapest, 1996.
- A Heuristic Model for Scheduling Large Projects with Limited Resources Author(s): Jerome D. Wiest Source: Management Science, vol. 13, No. 6, Series B, Managerial (Feb. 1967), pp. B359-B377.