Patents
US 7,987,080 B2#67690333 Most CitedActiveUnited States (USPTO)Utility

Method for operating an industrial scale installation and guidance system for same

0Forward Citations (#67690333 Global)
0.0/yrCitation Velocity (#67690333 Global)
0.56Citation PageRank (#67690333 Global)
13Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

A method and a guidance system for operating an industrial scale installation, especially a power plant installation, are provided. For this method and guidance system a number of installation operating parameters characterizing the operating state of the installation and several component operating parameters of selected components of the installation are monitored and stored in a memory device. A characteristic fatigue value characterizing the current fatigue state of each component is determined, as required, using the stored installation operating parameters and/or the stored associated component operating parameters. The purpose of this method and guidance system is to develop an operation of the installation which protects resources. To this end, an associated fatigue prognosis value is determined from the characteristic fatigue value characterizing the current fatigue state for each selected component using guiding parameters characterizing a planned change of state.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 13 · Forward citations: 0.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method for operating an industrial scale installation, comprising: monitoring a component operating parameter for a component of the industrial scale installation; monitoring an installation operating parameter for an operating state of the industrial scale installation; storing the component operating parameter in a storage facility; storing the installation operating parameter in the storage facility; determining a characteristic fatigue value for a current fatigue state of the component using the installation operating parameter and/or the component operating parameter; determining a pred

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.

Non-Patent Literature (3)

  • DIN EN 12952-4: Oct. 2001 "Water-tube boilers and auxiliary installations, Part 4: In service boiler life expectancy calculations, German version EN 12952-4: 20-00", pp. 1-18.
  • Mukhopadhyay et al., On-Line Fatigue-Creep Monitoring System for High-Temperature Components of Power Plants, International Journal of Fatigue, vol. 23, Iss. 6, Jul. 2001, pp. 549-560.
  • Park et al., Evaluation of an Energy-Based Approach and a Critical Plane Approach for Predicting Constant Amplitude Multiaxial Fatigue Life, International Journal of Fatigue, vol. 22, Iss. 1, Jan. 2000, pp. 23-39.