Distributed temperature sensing in deep water subsea tree completions
Abstract
A deep water subsea tree completion having a distributed temperature sensing system. In a described embodiment, a method of installing an optical fiber in a well includes the steps of: conveying an optical fiber section into the well; and monitoring a light transmission quality of the optical fiber section while the section is being conveyed into the well.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 50 · Forward citations: 6.
Claims (3 — 1 Independent, 2 Dependent)
- Claim 1Independent Claim
A method of installing an optical fiber in a well, the method comprising the steps of: conveying a first optical fiber section into the well, an end of the first optical fiber section being coupled to a first optical connector which is not connected to a mating second optical connector; and monitoring a light transmission quality of the first optical fiber section while the first section is being conveyed into the well.
- Claim 2Depends on #1
The method of claim 1 , further comprising the steps of: conveying a second optical fiber section into the well prior to conveying the first section into the well; and connecting the first and second sections to each other in the well.
- Claim 3Depends on #2
The method of claim 2 , wherein in the monitoring step, the light transmission quality includes a quality of a connection made between the first and second sections in the connect
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (6 of 6 total)
References Cited — Backward Prior Art (50)
Non-Patent Literature (5)
- "Pioneering Fibre Optic Completion Installation in the Mahogany Field, Offshore Trinidad," undated.
- Focal Technologies Corporation, Product Brochure for Model 286, dated Apr. 15, 2003.
- Halliburton Energy Services drawing No. 42 00 210 dated Apr. 7, 2001.
- Halliburton presentation entitled, "DTS Conceptual Completions," Dec. 3, 2002.
- Halliburton presentation entitled, "Greater Plutonio Completions Workshop," dated Mar. 12, 2003.