Finite capacity scheduling using job prioritization and machine selection
Abstract
In a method, device, and computer-readable medium for finite capacity scheduling, heuristic rules are applied in two integrated stages: Job Prioritization and Machine Selection. During Job Prioritization (“JP”), jobs are prioritized based on a set of JP rules which are machine independent. During Machine Selection (“MS”), jobs are scheduled for execution at machines that are deemed to be best suited based on a set of MS rules. The two-stage approach allows scheduling goals to be achieved for performance measures relating to both jobs and machines. For example, machine utilization may be improved while product cycle time objectives are still met. Two user-configurable options, namely scheduling model (job shop or flow shop) and scheduling methodology (forward, backward, or bottleneck), govern the scheduling process. A memory may store a three-dimensional linked list data structure for use in scheduling work orders for execution at machines assigned to work centers.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 39 · Forward citations: 46.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A computing device comprising: a processor; and persistent storage memory in communication with said processor storing processor readable instructions for directing said device to schedule a plurality of work orders, each work order of said plurality being defined by a plurality of operations to be scheduled at a plurality of work centers, each work center having a group of machines, each work center for performing an operation, the scheduling comprising, upon receiving a shop model indication comprising a job shop model and receiving an indication of a scheduling methodology comprising one of
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (15 of 46 total)
References Cited — Backward Prior Art (39)
Non-Patent Literature (5)
- Computer and Industrial Engineering, vol. 33 Issue 1-2, pp. (2) 249-252, 1997.
- Computer and Industrial Engineering, vol. 35, issue 1-2, Oct. 1998, pp. 113-116.
- Computer and Industrial Engineering, vol. 39 2001, pp. 307-324.
- Computers and Industrial Engineering, vol. 44 Issue: 1, 2002, pp. 119-131.