US 7,900,508 B2#39116012 Most CitedActiveUnited States (USPTO)Utility

Methods for controlling and making particle filtering devices

2Forward Citations (#39116012 Global)
0.1/yrCitation Velocity (#41576703 Global)
1.04Citation PageRank (#39657231 Global)
5Prior Art Cited
3Claims (1 Indep. · 2 Dep.)
0Drawings / Sheets

Abstract

One subject of the invention is a process for checking the robustness of a particulate filter intended to be used in the exhaust line of a diesel engine, comprising the steps consisting in, having first determined the soot mass limit of the filter, loading a new filter with a level of soot at least equal to two times and at most equal to three times the soot mass limit, then making the filter undergo a severe regeneration then, in any order, determining the filtration efficiency of the filter, measuring its pressure drop and comparing it to the pressure drop of the new filter, measuring its level of cracking, and finally checking its integrity after a mechanical stress. Another subject of the invention is a method for diagnosing the robustness of a filter.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 5 · Forward citations: 2.

Claims (3 — 1 Independent, 2 Dependent)

  1. Claim 1Independent Claim

    A process for checking the robustness of a particulate filter intended to be used in the exhaust line of a diesel engine, comprising the steps of: determining first the soot mass limit of said filter, loading a new filter with a level of soot at least equal to two times and at most equal to three times said soot mass limit, then making said filter undergo a severe regeneration and then, in any order: determining the filtration efficiency of said filter; measuring its pressure drop and comparing it to the pressure drop of the new filter; measuring its level of cracking; and finally checking its

  2. Claim 2Depends on #1

    The process as claimed in claim 1 , wherein the new filter is loaded with a level of soot of around two and a half times its soot mass limit.

  3. Claim 3Depends on #1

    The process as claimed in claim 1 , wherein the determinat

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗