Method and system for performing operations on a wind turbine
Abstract
A wind turbine has a nacelle frame and a first hoist substantially permanently mounted on the frame. The method comprises the processes of hoisting a second, more powerful hoist and crane on the frame with the first hoist; removably mounting the second hoist and the crane on the nacelle frame; hoisting a winch using the second hoist and the crane on the frame, and removably mounting the winch on said frame; performing operations involving handling heavy parts employing said winch; and removing and lowering said winch, crane, and second hoist from the frame.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 10 · Forward citations: 30.
Claims (3 — 2 Independent, 1 Dependent)
- Claim 1Independent Claim
A method of providing heavy lift capability to a wind turbine having a nacelle frame and a first hoist substantially permanently mounted on said nacelle frame for maintenance operations, said method comprising: utilizing said first hoist to lift a second hoist on said nacelle frame, said second hoist capable of lifting a heavier load than said first hoist; mounting said second hoist on said nacelle frame; mounting a crane proximate a rear portion of said nacelle frame; utilizing said second hoist and said crane to lift a winch to said nacelle frame; mounting said winch to said nacelle frame; a
- Claim 2Depends on #1
The method of claim 1 , wherein mounting said crane on said nacelle frame is completed such that said crane is removable.
- Claim 3Independent Claim
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗