Electron beam welding of sputtering target tiles
Abstract
Embodiments of the invention provide a method of welding sputtering target tiles to form a large sputtering target. Embodiments of a sputtering target assembly with welded sputtering target tiles are also provided. In one embodiment, a method for welding sputtering target tiles in an electron beam welding chamber comprises providing strips or powder of sputtering target material on a pre-determined at least one interfacial line between at least two sputtering target tiles, that are yet to be placed, on a surface of support, placing the at least two sputtering target tiles side by side with edges of the at least two sputtering target tiles abutting and forming at least one interfacial line on top of the strips or powder of sputtering target material, pumping out the gas in the electron beam welding chamber, preheating the at least two sputtering target tiles and the strips or powder of sputtering target material to a pre-heat temperature less than the temperature at which the at least two target tiles begin to melt, undergo a change in physical state, or undergo substantial decomposition, and welding the at least two sputtering target tiles placed side by side into a large sputterin
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 50 · Forward citations: 3.
Claims (3 — 1 Independent, 2 Dependent)
- Claim 1Independent Claim
A method for welding sputtering target tiles, comprising: placing at least two sputtering target tiles side by side on a surface of support with edges of the at least two sputtering target tiles abutting and forming at least one interfacial line; placing strips or powder of sputtering target material under the at least one interfacial line between the at least two target tiles before welding the at least two sputtering target tiles; and welding the at least two sputtering target tiles placed side by side into a sputtering target.
- Claim 2Depends on #1
The method of claim 1 , wherein the gap spacing of the at least one interfacial line between the edges of the at least two sputtering target tiles is less than 0.5 mm.
- Claim 3Depends on #1
The method of claim 1 , wherein the gap spacing of the at least one interfacial line between the edges of the at least two sputtering target tiles is
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (3 of 3 total)
References Cited — Backward Prior Art (50)
Non-Patent Literature (5)
- First Office Action for Chinese Patent Application No. 2005101381995 dated Aug. 29, 2008.
- Introducing the Largest Electron Beam Welding Machine in the USA! http://www.stadco.com/EBWeldIntro.htm.
- Lawrence Kren, "New 'window' of Opportunity for E-beam Welding", www.acceleron-enbeam.com.
- MFD Electron Beam Welding: A Brief Introduction to E Beam Welding. http://www-group.slac.stanford.edu/mfd/ebeam.html.
- Mick Lalley, "Laser Welding", Materials World, vol. 2, pp. 573, Nov. 1994.