Method and apparatus for planning, monitoring, and illustrating multiple tasks based on user defined criteria and predictive ability
Abstract
Individual employees arc permitted to be individuals and plan their work as individuals. Individuals are only asked to plan their work within a limited tasking horizon. Employees track their progress using verbs that are designed to capture the reasons behind positive and negative predictive ability. Verbs are analyzed and expected predictive error, also know as risk, is calculated. Once verbs arc captured they can be analyzed for ways to improve predictive ability. In addition, the risk can be factored into the initial planning stage so as to include an expected predictive error in the initial planning. The cost, effort, churn and risk values of projects are then illustrated in a comparison form with historical limitations from past similar projects.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 30 · Forward citations: 2.
Claims (2 — 1 Independent, 1 Dependent)
- Claim 1Independent Claim
A method for managing a project, comprising the steps of: setting a tasking horizon based on a predetermined time interval for parsing a time span for performing the project into a series of consecutive tasking horizons; identifying a tasking horizon for at least one task having at least one task related event expected to occur during said identified tasking horizon; receiving a respective predicted date for said at least one task related event expected to occur during said identified tasking horizon; receiving a corresponding actual date for each task related event for which a predicted date
- Claim 2Depends on #1
The method according to claim 1 , further comprising the step of: producing a multi-dimensional graphical display repr
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (2 of 2 total)
| Patent | Title | Year | Citations |
|---|---|---|---|
| US 2008278494 A1 | System and method for information display | — | 3 |
| US 8,374,905 B2 | Predicting success of a proposed project | 2013 | 9 |
References Cited — Backward Prior Art (30)
Non-Patent Literature (3)
- AbouRizk et al., "Construction Simulation and Distribution Fitting in a Data Deficient Environment" Uncertainty Modeling and Analysis, Second National Symposium on College Park, MD, Apr. 1993, pp. 493-499.
- W.R. Duncan, "A Guide to the Project Management Body of Knowledge", Guide to the Project Management Body of Knowledge, 1996, pp. 4-10, 30.
- William R. Duncan, "A Guide to the Project Management Body of Knowledge," Project Management Institute, 1996; p. 8-10, p. 30-32, p. 42, p. 59-62, p. 70, p. 107-108; p. 157-171.