One embodiment of the present invention provides for a subterranean structure, having a continuous ribbon slab having a plurality of flights fabricated from concrete. The ribbon slab defines periodic openings therein which generally align between adjacent flights. Another embodiment provides for a method of fabricating a subterranean structure. The method includes excavating soil to form a downward sloping ramp, and forming a concrete slab on the downward sloping ramp. The method further includes continuing to excavate soil to extend the downward sloping ramp to a location under the concrete slab, and continuing to form the concrete slab on the downward sloping ramp so that a subterranean structure is formed having an essentially continuous concrete slab with a first portion which is above and spaced-apart from a second portion.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 18 · Forward citations: 4.

Claims (2 — 1 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    A method of fabricating a subterranean structure, comprising: excavating soil to form a downward sloping ramp; forming a concrete slab on the downward sloping ramp; continuing to excavate soil to extend the downward sloping ramp to a location under the concrete slab; continuing to form the concrete slab on the downward sloping ramp so that a subterranean structure is formed having an essentially continuous concrete slab with a first portion which is above and spaced-apart from a second portion; and prior to the excavating, driving plural sheet piles to define an inner perimeter and an outer pe

  2. Claim 2Depends on #1

    The method of claim 1 , and further comprising: driving plural sheet piles downward from the second portion to further define the i