Welding process
Abstract
A process for repairing a compressor rear frame of a gas turbine engine. The process entails removing a seal flange from the inner casing wall of the frame to define an annular face on the casing wall, and fabricating a replacement flange to have an annular face with a radial width greater than the radial width of the annular face of the casing wall. The faces of the flange and wall are mated to form a joint, a penetration-enhancing flux is deposited adjacent the joint, and a single-pass gas tungsten arc welding operation is performed to form a root weldment that extends completely through the joint. The flux is then removed and a gas tungsten arc welding operation is performed to deposit a filler on the root weldment and form a second weldment that completely overlays but does not penetrate through the root weldment.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 4 · Forward citations: 19.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A process for repairing a compressor rear frame of a gas turbine engine, the compressor rear frame comprising a cylindrically-shaped inner casing wall and a cylindrically-shaped outer casing wall that substantially circumscribes the inner casing wall, the inner casing wall having a flange adapted to carry a seal member, the process comprising the steps of: removing the flange from the inner casing wall to define an annular face on the inner casing wall, the annular face having a width; fabricating a replacement flange to have an annular face with a width that is greater than the width of the a
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (15 of 19 total)
References Cited — Backward Prior Art (4)
Non-Patent Literature (1)
- Edison Welding Institute, INSIGHTS Materials Joining Newsletter; Spring 2003, vol. 16, No. 2; "EWI Develops Full-Scale Riser Fatigue Test Facility in Columbus, Ohio".