Patents
US 6,729,802 B2#2572761 Most CitedExpiredUnited States (USPTO)Utility

System and method for abandoning and recovering pipeline

28Forward Citations (#2572761 Global)
1.3/yrCitation Velocity (#4636934 Global)
3.29Citation PageRank (#6524251 Global)
34Prior Art Cited
3Claims (2 Indep. · 1 Dep.)
0Drawings / Sheets

Abstract

A method of abandoning a pipeline ( 2 ) being laid by a vessel having an A/R system, wherein a sealine ( 2, 11, 13 ) is initially held by a pipe laying and tensioning arrangement. The method includes a step of reducing tension at sea level of the sealine ( 2, 11, 13 ), by connecting one or more buoyant members ( 13 ) to the end of the pipeline ( 2 ). The members ( 13 ) are then lowered into the sea, using a line ( 16 ). At least one member ( 13 ) is connected to the pipeline ( 2 ) through a connection ( 12 ) which allows pivoting of the member ( 13 ) so that the end of the member ( 13 ) at the end of the pipeline ( 2 ) projects upwardly from the seabed ( 3 ).

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 34 · Forward citations: 28.

Claims (3 — 2 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    A method of abandoning a pipeline being J-laid by a vessel, wherein a sealine comprising the pipeline is initially held by a pipe laying and tensioning arrangement, the method including the steps of reducing the tension at sea level of the sealine, and thereafter lowering the end of the sealine towards the seabed using a line from a winch on the vessel, thereby enabling the maximum load bearing capacity of the winch to be substantially less than the maximum load bearing capacity of the pipe laying and tensioning arrangement.

  2. Claim 2Depends on #1

    A method according to claim 1 , in which the step of reducing the tension at sea level of the sealine being laid by the vessel comprises connecting one or more light elongate members to the end of the pipeline and lowering the elongate members into the sea.

  3. Claim 3Independent Claim

    A method according to cla

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (1)

  • Robert T. Gilchrist Jr., "Here are Design Procedures for Installing Deepwater Plem", XP-000833530, pp. 63-64, 66-68, 70-71, Feb. 11, 1998, Deepwater Technology, Second-End Plem Installation Phases.