Patents
US 6,571,872 B2#5053206 Most CitedExpiredUnited States (USPTO)Utility

Apparatus for completing wells in unconsolidated subterranean zones

18Forward Citations (#5053206 Global)
0.8/yrCitation Velocity (#9583059 Global)
2.00Citation PageRank (#14557962 Global)
49Prior Art Cited
2Claims (1 Indep. · 1 Dep.)
0Drawings / Sheets

Abstract

Improved methods and apparatus for completing an unconsolidated subterranean zone penetrated by a well bore are provided. The methods basically comprise the steps of placing a slotted liner having an internal sand screen disposed therein with dividers extending between the screen and liner, isolating the slotted liner and the well bore in the zone and injecting particulate material into flow paths formed by the dividers between the sand screen and the slotted liner and into the annulus between the slotted liner and the well bore to thereby form packs of particulate material therein to prevent the migration of fines and sand with produced fluids

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 49 · Forward citations: 18.

Claims (2 — 1 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    An assembly for disposal within a borehole for a well comprising: a liner member having a wall forming a bore and a plurality of perforations through said wall; a screen member having at least one screen disposed within said bore and forming an inner annulus with said liner member; a plurality of channelizer members extending between said liner and screen member and extending at least the length of the at least one screen dividing said inner annulus into a plurality of flow paths; wherein said flow paths define an aggregate flow area which remains substantially constant along said paths.

  2. Claim 2Depends on #1

    The assembly of claim 1 , wherein said perforations have a first flow area, said first flow area having a predetermined size as compared to said aggregate flow area defined by said flow paths.

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (3)

  • Conceptual Development; concentric Alternate Path Screen Project; Nov. 3, 1998; (pp. 1-7).
  • L. Jones; Petroleum Engineer International; Fracpacking Horizontal Wells Allows Ultra-High Rates From Mediocre Formations; Jul. 1999; (pp. 37-40).
  • Schlumberger Dowell; Alternate Path + Services; Feb. 1997; (p. 9).