Abstract

In a land based gas turbine including a compressor, a combustor and turbine section including at least three stages, an improvement comprising an inlet into a third stage nozzle from the compressor for feeding cooling air from the compressor to the third stage nozzle; at least one passageway running substantially radially through each airfoil of the third stage nozzle and an associated diaphragm, into an annular space between the rotor and the diaphragm; and passageways communicating between the annular space and individual buckets of the third stage.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 2 · Forward citations: 37.

Claims (2 — 1 Independent, 1 Dependent)

  1. Claim 1Independent Claim

    In a land based gas turbine comprising a compressor, a combustor and turbine section including at least first, second and third stages, a cooling circuit comprising: an inlet into a third stage nozzle from the compressor for feeding cooling air from the compressor to the third stage nozzle; at least one passageway running substantially radially through each airfoil of said third stage nozzle and an associated diaphragm, into an annular space between the rotor and the diaphragm; and passageways communicating between said annular space and individual buckets of said third stage; wherein said at

  2. Claim 2Depends on #1

    The gas turbine of claim 1 wherein said portion of said at least one passa

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

References Cited — Backward Prior Art (2)

Non-Patent Literature (5)

  • "39th GE Turbine State-of-the-Art Technology Seminar", Tab 1,""F" Technology-the First Half-Million Operating Hours", H.E. Miller, Aug. 1996.
  • "39th GE Turbine State-of-the-Art Technology Seminar", Tab 10, "Gas Fuel Clean-Up System Design Considerations for GE Heavy-Duty Gas Turbines", C. Wilkes, Aug. 1996.
  • "39th GE Turbine State-of-the-Art Technology Seminar", Tab 11, "Integrated Control Systems for Advanced Combined Cycles", Chu et al., Aug. 1996.
  • "39th GE Turbine State-of-the-Art Technology Seminar", Tab 12, "Power Systems for the 21st Century "H" Gas Turbine Combined Cycles", Paul et al., Aug. 1996.