Patents
US 6,374,591 B1#785599 Most CitedExpiredUnited States (USPTO)Utility

Liquified natural gas (LNG) fueled combined cycle power plant and a (LNG) fueled gas turbine plant

55Forward Citations (#785599 Global)
2.3/yrCitation Velocity (#1569417 Global)
6.77Citation PageRank (#2020779 Global)
16Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

A process and system which improves the capacity and efficiency of a power plant. A LNG supply system fuels the plant. Gasified LNG in a combustor mixes with the air from an air compressor to provide the hot combustion gas for a gas turbine. The expanding LNG is used to chill a heat exchange fluid, e.g. water, which heat exchange fluid cools and densifies the intake air for the air compressor. Subsequently, the heat exchange fluid is used in another heat exchange step and is then re-chilled and recycled to cool and densify the intake air.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 16 · Forward citations: 55.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method for enhancing the capacity and efficiency of a gas turbine plant which comprises: flowing LNG into a regasifier/chiller; flowing a heat exchange fluid into the regasifier/chiller to regasify the LNG and to chill the heat exchange fluid; flowing the chilled heat exchange fluid through a heat exchange zone through which zone flows the intake air for an air compressor in the gas turbine plant, the heat exchange fluid cooling and densifying the intake air; flowing the heat exchange fluid from the heat exchange zone through a heat recovery heat exchanger to warm the heat exchange fluid; fl

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Non-Patent Literature (1)

  • Section 3.0 Description of the Project from the "Petition Before the Massachusetts Energy Facilities Council for Approval to Construct a Bulk Generating Facility Island End Congeneration Project", dated Mar. 1991, prepared by Cabot Power Corporation et al. and submitted by Cabot Power Corporation.