US 4,881,848 A#9947179 Most CitedExpiredUnited States (USPTO)Utility

Method of forming an immersed dam foundation and a dam structure thereon

10Forward Citations (#9947179 Global)
0.3/yrCitation Velocity (#27282397 Global)
3.06Citation PageRank (#7324305 Global)
8Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

An immersed dam foundation and a dam structure are formed in a body of moving water by forming a plurality of spaced piers having temporary support posts thereon. A current deflector is secured to the upstream support posts and sheet piling walls are driven to form upstream and downstream walls between the piers forming a base therebetween. The base is covered with a tremie seal and the walls cut off so that a prefabricated dam structure can be floated to a location above the tremie seal and lowered onto anchor points on the adjacent piers and secured to the piers and tremie seal. An exposed face of a pier is protected from the currents by barriers that serve as a portion of the next upstream and downstream walls, with gravel covered by precast concrete pads. The access galleries of adjacent prefabricated dam structures are closely aligned and seals provided therebetween.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 8 · Forward citations: 10.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method of constructing an immersed dam foundation, in a body of moving water having a floor, and of forming a dam structure thereon, without the requirement for large cofferdams that block large portions of the body of water for long time periods, comprising: forming a plurality of laterally spaced support piers, having upstream and downstream ends, below the surface of the body of moving water, the piers having spaced stable anchor points thereon, and sheet piling about the perimeter thereof; constructing a first temporary support post on the upstream end of each pier and a second tempora

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗