Sootblowing optimization
Abstract
A method for predicting the optimum cycle time to schedule sootblowing using on-line process measurements. The optimum cycle times dynamically adjust to changing conditions resulting from boiler operation, fuel changes, or seasonal changes. The optimum cycle time is calculated four times per second for each heat trap of a boiler (10). The optimum conditions are based on economic criteria which account for heat trap fouling, rate of fouling of other heat traps (12, 13, 14, 16, and 18) within the boiler, and on-line boiler incremental steam cost.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 6 · Forward citations: 31.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A method of optimizing cycle time (θ opt ) to schedule sootblowing during the operation of a boiler having an input of fluid with a particular specific heat (c p ) to generate steam at a particular cost per unit of heat in the boiler comprising: sensing the input and output temperatures of fluid to and from a boiler to obtain a difference (Δt) of input and output temperatures, sensing a flow rate (m) of the fluid in the boiler during its operation, determining an incremental cost of steam (Φ), with the time for actual sootblowing (θ c ) being known to determine the cost of steam for sootblowin
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗