Patents
US 4,363,101 A#3542831 Most CitedExpiredUnited States (USPTO)Utility

Computerized power demand control in an electrochemical plant

22Forward Citations (#3542831 Global)
0.5/yrCitation Velocity (#15132250 Global)
17.36Citation PageRank (#423473 Global)
10Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

All line control is performed with a power demand control system to bring about ideal rate before the end of a demand period. Demand error is modified so as to project the demand toward a definite point on the ideal rate curve, then to follow the ideal rate toward the target. Correction at a chosen point in time takes into account a possible duration from ideal rate consumption by either choosing the ideal rate short of the target or by pointing exactly to the target. All lines are individually controlled by tap changing with variable deadband and hysteresis, and tap moves are estimated on the basis of individual wattage and amperage changes in a previous control cycle. The minimum between necessary tap moves and the tap moves possible within an upper and a lower limit in the cell line amperage is used for control. The system allows safe settings by the operator and establishes passwords to communicate with the computer system when protected steps are to be dealt with, by the engineer, for instance.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 10 · Forward citations: 22.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method of controlling the loads in a plant facility while keeping the overall plant consumption within an assigned power demand limit, comprising the steps of: measuring the actual power rate of consumption by said plant; establishing successive demand periods for totalizing the power demand from the beginning of a demand period to the end thereof; said power demand limit being assigned at the end of a demand period; periodically calculating a demand error projected to be at the end of a demand period on the basis of actual power rate; changing concurrently with said calculating step

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗