US 4,028,792 A#1470198 Most CitedExpiredUnited States (USPTO)Utility

Method of erecting a tower crane from two groups of modular tower sections differing in cross section

39Forward Citations (#1470198 Global)
0.8/yrCitation Velocity (#9102409 Global)
4.90Citation PageRank (#3427936 Global)
4Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

A tower crane is erected from a boom assembly, first and second tower sections of different cross section, and a base in a sequence of steps in which the boom assembly is mounted on a hollow climbing section dimensioned to be received in each of the larger second tower sections and defining a cavity dimensioned to receive each of the first tower sections. One of the latter is secured on a base in upright position, and the upright section is received in the cavity of the climbing section which is then raised relative to the first section and enveloped by one of the second sections. The enveloping section is secured to the base and the raised climbing section for supporting the climbing section whereupon the first tower section may be rleased from the base, raised, and secured to the second tower section. The climbing section may then be raised relative to the first tower section to permit the installation of another second section, and the procedure repeated, until all second or larger tower sections are superimposed on each other, the one first section being ultimately attached to the topmost second section. When the climbing section is raised relative to the attached first section

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 4 · Forward citations: 39.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    A method of erecting a tower crane from a boom assembly, a plurality of first modular tower sections, a plurality of second, tubular, modular tower sections of larger cross section than said first sections, and a base, which comprises the steps of: a. mounting said boom assembly on a hollow climbing section dimensioned to be received in each of said second sections and defining a cavity dimensioned to receive each of said first sections, said cavity being open in at least one direction; b. securing one of said first sections on said base in an upright position, and receiving the upright sect

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗