Patents
US 3,968,655 A#3002281 Most CitedExpiredUnited States (USPTO)Utility

Method of reinforcing tunnels before excavation

25Forward Citations (#3002281 Global)
0.5/yrCitation Velocity (#15151497 Global)
4.65Citation PageRank (#3731899 Global)
3Prior Art Cited
1Claims (1 Indep. · 0 Dep.)
0Drawings / Sheets

Abstract

This invention relates to a method of reinforcing tunnels which comprises driving a crown drift along the top of the proposed tunnel, driving a pair of wall plate drifts along opposite sides of the proposed tunnel in spaced substantially parallel relation beneath and to one side of the crown drift, drilling a longitudinally spaced aligned or staggered series of small diameter bores downwardly and outwardly in both directions from within the crown drift along the ceiling of the proposed tunnel, drilling other series of similar bores upwardly from within the wall plate drifts along the walls of the proposed tunnel, said ceiling and wall bordering bore patterns being inclined toward one another and of a length such as to produce a skewed overlapped relation, inserting reinforcing rods into the bores of each series thereof so as to produce a metal curtain between drifts bordering the perimeter of the proposed tunnel, grouting the rods permanently in place within their respective bores, filling the drifts back up with concrete and removing the material within the arch defined by the refilled drifts and metal curtain therebetween. The invention also encompasses a method wherein the addit

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 3 · Forward citations: 25.

Claims (1 — 1 Independent, 0 Dependent)

  1. Claim 1Independent Claim

    The method of reinforcing the perimeter rock bordering a tunnel formed through rock preparatory to excavating same which comprises the steps of: excavating a crown drift along the top of the proposed tunnel, excavating a pair of wall plate drifts along opposite sides of the proposed tunnel in spaced substantially parallel relation beneath and to the sides of the crown drift, drilling a longitudinally spaced series of small diameter bores downwardly and outwardly in both directions from within the crown drift along the ceiling of the proposed tunnel, drilling other series of similar bores upwar

Technical Overview & Description

Full multi-page specification text is archived at the issuing office. Read complete official specification ↗

Cited By — Indexed Forward Citations (15 of 25 total)

PatentTitleYearCitations
US 2011116868 A1Method for constructing an underground tunnel or hole to create an impervious plug for the storage of hazardous, particularly radioactive, waste—6
CN 113,503,166 AReinforced disposal structure for karst cave at middle lower part of tunnel and construction method thereof—6
WO 2010/007305 A3Method for constructing an underground tunnel or hole to create an impervious plug for the storage of hazardous, particularly radioactive, waste—1
US 4,405,260 AMethod of constructing underpass across railway and highway without affecting normal traffic thereof198335
CN 114,109,442 BTunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method20240
CN 114,960,741 AStaggered double-hole small-clear-distance tunnel portal section supporting structure and construction method—0
US 5,211,507 AMethod of making a huge elongated space of square or rectangular cross section under the ground19935
CN 108,952,771 AExisting rigid structures zero are worn under one kind deforms construction method—0
US 4,422,798 AProcess for construction of an underground structure and the structure thus obtained198310
US 5,199,817 AProcess of providing an elongate underground cavity19935
JP 2011528119 A有害廃棄物、特に、放射性廃棄物を保管するための不浸透性のプラグを形成するための地下トンネル又は穴の建設方法—0
CN 111,075,471 ALarge karst cavity top filling type tunnel rockfall prevention structure and construction method—2
US 5,104,259 AMethod for excavating rock cavities19923
US 4,084,384 AAdvanced slot stress control method of underground excavation197810
CN 111,997,623 ATunnel curtain grouting construction method—2