US 12,809,348 B2#155753662 Most CitedActiveUnited States (USPTO)Utility

Method for operating cell based mobility production system

0Forward Citations (#155753662 Global)
0.0/yrCitation Velocity (#155753662 Global)
0.00Citation PageRank (#155753662 Global)
15Prior Art Cited
18Claims (3 Indep. · 15 Dep.)
6Drawings / Sheets

Abstract

An embodiment method of operating a cell-based mobility production system for producing various types of mobilities includes assigning works required in each cell of a plurality of cells connected in series or in parallel that vehicle bodies need to go through based on the type of the mobility to be produced, determining a feeding order of the vehicle bodies based on the assigned works, and reassigning the works required in each cell that the vehicle bodies to be fed need to go through based on the determined feeding order, wherein each of assigning the works, determining the feeding order, and reassigning the works is performed by a processor.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 15 · Forward citations: 0.

Claims (18 — 3 Independent, 15 Dependent)

  1. Claim 1Independent Claim

    A method of operating a cell-based mobility production system for producing various types of mobilities, the method comprising: assigning works required in each cell of a plurality of cells connected in series or in parallel that vehicle bodies need to go through based on a type of a mobility to be produced; determining a feeding order of the vehicle bodies based on the assigned works and the type of the mobility to be produced; reassigning the works required in each cell that the vehicle bodies to be fed need to go through based on the feeding order of the vehicle bodies; and assembling the various types of mobilities by performing the reassigned works on the vehicle bodies fed into each cell, wherein: each of assigning the works, determining the feeding order, and reassigning the works is performed by a processor, and reassigning the works comprises reassigning the works required in each cell for the vehicle bodies to be fed based on the determined feeding order and workload differences between a preceding vehicle body and a following vehicle body so as to minimize idle time between adjacent cells.

  2. Claim 2Depends on #1

    The method of claim 1, wherein reassigning the works required in each cell comprises reassigning the works such that a total production time of the vehicle bodies to be fed according to the determined feeding order satisfies a minimum production time.

  3. Claim 3Depends on #1

    The method of claim 1, further comprising: after reassigning the works, detecting a work delay in a specific cell when the vehicle bodies are fed based on the determined feeding order; and reassigning the works again in response to detecting the work delay.

  4. Claim 4Depends on #1

    The method of claim 1, wherein reassigning the works comprises: preparing a plurality of expected reassignments in which the works required in each cell for the vehicle bodies to be fed based on the determined feeding order are assigned; and selecting an optimal reassignment from among the plurality of expected reassignments, wherein a total production time of the vehicle bodies to be fed based on the determined feeding order satisfies a minimum production time in the optimal reassignment.

  5. Claim 5Depends on #1

    The method of claim 1, wherein determining the feeding order of the vehicle bodies comprises: preparing a plurality of expected production plans different from each other in the feeding order of the vehicle bodies; and selecting an optimal expected production plan from among the plurality of expected production plans that has a shortest total working time.

  6. Claim 6Depends on #1

    The method of claim 1, wherein determining the feeding order of the vehicle bodies comprises: preparing a plurality of expected production plans different from each other in the feeding order of the vehicle bodies; and selecting an optimal expected production plan from among the plurality of expected production plans that has a shortest standby time.

  7. Claim 7Depends on #1

    The method of claim 1, wherein reassigning the works comprises reassigning the works required in each cell for the vehicle bodies to be fed based on the determined feeding order and possible and impossible works in the respective cells.

  8. Claim 8Depends on #1

    The method of claim 1, further comprising planning a logistics flow required in each cell based on the feeding order and the reassigned works.

  9. Claim 9Independent Claim

    A method of operating a cell-based mobility production system for producing various types of mobilities, the method comprising: assigning works required in each cell of a plurality of cells connected in series or in parallel that vehicle bodies need to go through based on a type of a mobility to be produced; determining a feeding order of the vehicle bodies based on the assigned works and the type of the mobility to be produced; reassigning the works required in each cell that the vehicle bodies to be fed need to go through based on the feeding order of the vehicle bodies; and assembling the various types of mobilities by performing the reassigned works on the vehicle bodies fed into each cell, wherein reassigning the works comprises reassigning the works required in each cell for the vehicle bodies to be fed based on the determined feeding order and workload differences between a preceding vehicle body and a following vehicle body so as to minimize idle time between adjacent cells.

  10. Claim 10Depends on #9

    The method of claim 9, further comprising planning a logistics flow required in each cell based on the feeding order and the reassigned works.

  11. Claim 11Depends on #10

    The method of claim 10, further comprising: after planning the logistics flow, detecting an occurrence or non-occurrence of a logistics flow issue during feeding of the vehicle bodies based on the feeding order; and performing planning the logistics flow again in response to detecting the occurrence of the logistics flow issue.

  12. Claim 12Depends on #11

    The method of claim 11, wherein the logistics flow issue comprises a collision or congestion in the logistics flow.

  13. Claim 13Depends on #10

    The method of claim 10, further comprising: after planning the logistics flow, detecting a work delay in a specific cell when the vehicle bodies are fed based on the feeding order; and in response to detecting the work delay, performing reassigning the works and planning the logistics flow again.

  14. Claim 14Depends on #10

    The method of claim 10, further comprising, after planning the logistics flow, detecting possibility or impossibility of achieving a target production amount of each mobility when the vehicle bodies are fed based on the feeding order.

  15. Claim 15Depends on #14

    The method of claim 14, wherein detecting the possibility or impossibility comprises detecting the impossibility of achieving the target production amount, the method further comprising reassigning the works and planning the logistics flow again in response to detecting the impossibility of achieving the target production amount.

  16. Claim 16Depends on #14

    The method of claim 14, wherein detecting the possibility or impossibility comprises detecting the possibility of achieving the target production amount, the method further comprising fixing and applying a smart factory operation plan in response to detecting the possibility of achieving the target production amount.

  17. Claim 17Independent Claim

    A cell-based mobility production system for producing various types of mobilities, the cell-based mobility production system comprising: a plurality of cells connected in series or in parallel, wherein the cells are configured to receive vehicle bodies and modify the vehicle bodies based on a type of a mobility to be produced; and a processor configured to: assign works required in each cell of the plurality of cells based on the type of the mobility to be produced; determine a feeding order of the vehicle bodies to be fed based on the assigned works and the type of the mobility to be produced; reassign the works required in each cell based on the feeding order of the vehicle bodies; and control each of the plurality of cells to perform the reassigned works on the corresponding vehicle bodies to thereby assemble the various types of mobilities, wherein, to reassign the works, the processor is further configured to reassign the works required in each cell for the vehicle bodies to be fed based on the determined feeding order and workload differences between a preceding vehicle body and a following vehicle body so as to minimize idle time between adjacent cells.

  18. Claim 18Depends on #17

    The cell-based mobility production system of claim 17, wherein the processor is configured to reassign the works such that a total production time of the vehicle bodies to be fed based on the determined feeding order satisfies a minimum production time.

Technical Overview & Description

CROSS-REFERENCE TO RELATED APPLICATIONS This application claims the benefit of Korean Patent Application No. 10-2021-0113871, filed on Aug. 27, 2021, which application is hereby incorporated herein by reference. TECHNICAL FIELD The present invention relates to a method of operating a cell-based mobility production system. BACKGROUND Conventionally, an integrated mass production method of selected models centered on a conveyor has been maintained. In a conventional case, vehicles are fed in a predetermined sequence, and production is carried out by the repetitive operations in each process designated to respective vehicle models by a single work assignment until a finished vehicle is produced. When vehicles are produced by a single work assignment designated to the respective vehicle models, a work delay occurs due to a difference in working times between vehicle models if several vehicle models are simultaneously produced (mixed production). Accordingly, innovation in the manufacturing methods is necessary to move away from the traditional vehicle production toward quick and efficient production of a variety of vehicle models. An example of such a manufacturing method is a cell-based smart factory. In the cell-based smart factory, a unique work may be performed in each cell, the cells may be arranged in various ways in the factory, and the schedule regarding what cells vehicle bodies to be fed will go through may be readily changed. However, even in such a cell-based process, a well-prepared overall production plan is called for to minimize bottlenecks caused by vehicle model changes and increase production efficiency. Accordingly, a method of quick and accurate simulation and establishing of production plans in advance is needed. The matters described above as the technical background are intended only for a better understanding of the background of the present disclosure and should not be taken as an acknowledgment that they pertain to the conventional art already

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.