Clamp attachment for boom of telescopic handler and method of assembling and placing decking material on a building using the clamp attachment
Abstract
A boom clamp attachment has a gib frame, a boom quick-connect, a shaft arm axle, a shaft arm torque assembly, and at least one gib clamp assembly. The gib clamp assembly has a clamp support member having a first gib clamp at a first end and second gib clamp at a second end. The gib clamp has a fixed finger and a moveable finger, the moveable finger controlled via hydraulics. The boom clamp may hoist, tilt, and position an assembled section of panels.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 9 · Forward citations: 0.
Claims (8)
- Claim 1Independent Claim
A method of using a boom clamp attachment for maneuvering a section of panels, the method comprising: assembling a panel section at ground level, the panel section comprising a plurality of I-beams, wherein the panel section is assembled using one or more holding brackets, the one or more holding brackets comprising a spring to position the one or more holding brackets; placing the boom clamp attachment comprising (a) a gib frame extending longitudinally in relation to a boom and (b) a shaft arm axle comprising a plurality of gib clamp assemblies, beneath the assembled panel section via a telescopic handler, wherein each gib clamp assembly aligns, respectively, with an I-beam of the plurality of I-beams, each gib clamp assembly comprising a clamping mechanism; clamping each I-beam, respectively, using the clamping mechanism of each respective gib clamp assembly; and rotating the panel section via rotation of the shaft arm axle of the boom clamp attachment longitudinally in relation to
- Claim 2Independent Claim
A method of using a boom clamp attachment for maneuvering an assembled section of panels, the method comprising: coupling the boom clamp attachment to a boom of a telescopic handler; positioning the boom clamp attachment beneath an assembled panel section comprising decking material fastened to a plurality of structural members; aligning a plurality of gib clamp assemblies of the boom clamp attachment with the plurality of structural members, respectively; actuating a clamping mechanism of each respective gib clamp assembly to releasably clamp a respective structural member; lifting the assembled panel section with the telescopic handler; rotating the assembled panel section by rotating a shaft arm axle of the boom clamp attachment along a longitudinal axis and in relation to a gib frame of the boom clamp attachment to tilt the assembled panel section for positioning at an installation location; and releasing the assembled panel section by unclamping each respective structural member.
- Claim 3Depends on #2
The method of claim 2, wherein each gib clamp assembly comprises first and second grip plates configured to contact opposing sides of the respective structural member during the clamping step.
- Claim 4Depends on #2
The method of claim 2, wherein the plurality of structural members comprises a plurality of I-beams, wherein the clamping mechanism of each gib clamp assembly comprises first and second clamping protrusions each having a receiving aperture, and wherein releasably clamping the respective I-beam comprises receiving a lower flange of the respective I-beam in the receiving apertures.
- Claim 5Depends on #2
The method of claim 2, wherein each gib clamp assembly is secured to the shaft arm axle by a saddle and keyway arrangement configured to prevent unwanted rotation of the gib clamp assembly and maintain the plurality of gib clamp assemblies in a linear array on a common geometric plane during the rotating step.
- Claim 6Independent Claim
A method of assembling a panel section at ground level for installation on a building via a boom clamp attachment, the method comprising: positioning a plurality of I-beams in a plurality of holding brackets, respectively, each holding bracket comprising a receiving side movable between a receiving position and a lowered position; biasing the receiving side toward the receiving position using a spring; placing an I-beam of the plurality of I-beams into the receiving side such that, in response to a weight of the I-beam, the receiving side moves toward the lowered position to captivate the I-beam at a predetermined position; and after fastening decking material to the plurality of I-beams to form the panel section, lifting the panel section such that removal of the weight causes the receiving side to return toward the receiving position via the spring.
- Claim 7Depends on #6
The method of claim 6, wherein the receiving side comprises a V-shaped portion configured to funnel the I-beam to a center position.
- Claim 8Depends on #6
The method of claim 6, further comprising lifting the panel section using a telescopic handler having the boom clamp attachment, the boom clamp attachment comprising a plurality of gib clamp assemblies configured to releasably clamp the plurality of I-beams, respectively.
Technical Overview & Description
CROSS-REFERENCE TO RELATED APPLICATIONS This application is a continuation of U.S. Non-Provisional application Ser. No. 16/509,334, filed on Jul. 11, 2019, which claims the benefit of U.S. Provisional Application Ser. No. 62/696,436, filed on Jul. 11, 2018, both of which are incorporated herein by reference. TECHNICAL FIELD The present disclosure relates to building construction. More particularly, the present disclosure relates to a panelization system allowing for ground assembly of suspended building components (e.g., I-beams and panels) and placement of the assembled panels using a clamp attachment for a boom of a telescopic handler. BACKGROUND Building construction is a complex and dangerous environment. Often times, several workers must be hoisted to high elevations, where the workers precariously assemble building components. For example, currently in the art, a crane or telescopic handler must raise or hoist individual joist cross-beams into position where a worker must install fasteners to each end of the joist cross-beam, fastening them to girders supported by the building columns. After a sufficient number of joist cross-beams are installed, a decking crew would then receive a load of corrugated decking material via crane or boom forklift and then spread and fasten the decking material over the cross beams. As appreciated, working at this height is dangerous and laborious. Great physical labor is required in climbing to position, bolting cross beams, as well as shifting and attaching the decking. Simple mistakes can lead to injury. Therefore, there remains a need in the art for a system and method that reduces fall and injury risks, that reduces the number of workers working at elevated heights, that allows workers to assemble the decking material at ground level, and that allows for installation of the assembled decking panels with little labor. The current invention seeks to solve these and other problems. SUMMARY OF EXAMPLE EMBODIMENTS In one embodimen
Cited By — Indexed Forward Citations (0 of 0 total)
No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.
References Cited — Backward Prior Art (9)
| Patent | Title | Year | Citations |
|---|---|---|---|
| EP 3,462,025 A1 | Fluid system | — | 0 |