Doffing scheduling method for yarn spindle product, electronic device, and storage medium

0Forward Citations (#3125622 Global)
0.0/yrCitation Velocity (#3125622 Global)
0.00Citation PageRank (#3125622 Global)
21Prior Art Cited
5Structured Claims
0Drawings / Sheets

Abstract

Provided is a doffing scheduling method and apparatus for yarn spindle product, and storage medium, applied in an automatic doffing system, relating to the field of computer technology, and particularly to the field of automation control. The automatic doffing system is connected to an automated guided vehicle, (AGV) and an overhead rail doffing vehicle, the AGV and the overhead rail doffing vehicle being deployed in different vertical spaces within a target workshop. The method includes: determining a target doffing vehicle corresponding to a first winding machine in the target workshop from the AGV and the overhead rail doffing vehicle based on time-related information of doffing the yarn spindle product in all or part of winding machines in the target workshop; scheduling the target doffing vehicle to complete a doffing task of the yarn spindle product in the first winding machine.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 21 · Forward citations: 0.

Claims (5)

  1. Claim 1Independent Claim

    A doffing scheduling method for yarn spindle products, applied in an automatic doffing system which is in connection with an automated guided vehicle (AGV) and an overhead rail doffing vehicle, wherein the AGV is used to complete a dropping task of a yarn spindle product in at least one winding machine of a plurality of winding machines in a target workshop, the AGV is able to travel freely on ground without relying on a rail, the overhead rail doffing vehicle runs along a rail at a position of a certain height in the target workshop, and the AGV and the overhead rail doffing vehicle travel independently; wherein the method comprises: determining, by the automatic doffing system, whether the AGV is able to serve a first winding machine in the plurality of winding machines, by at least one of a), b) or c): a) determining, by the automatic doffing system, a number L of winding machines that the AGV is able to serve, based on a winding duration of a yarn spindle product to be processed in

  2. Claim 2Depends on #1

    The method of claim 1, wherein the scheduling of the target doffing vehicle to complete the doffing task of the yarn spindle product in the first winding machine comprises: determining, by the automatic doffing system, in the case where the target doffing vehicle is the AGV, a travel route of the AGV based on a position of the first winding machine; and scheduling, by the automatic doffing system, based on the travel route of the AGV, the AGV to deliver the yarn spindle product from the first winding machine to the yarn receiving station.

  3. Claim 3Depends on #1

    The method of claim 1, wherein the scheduling of the target doffing vehicle to complete the doffing task of the yarn spindle product in the first winding machine comprises: scheduling, by the automatic doffing system, in the case where the target doffing vehicle includes the overhead rail doffing vehicle, the overhead rail doffing vehicle to deliver the yarn spindle product from the first winding machine to the yarn receiving station via a rail based on a position of the first winding machine.

  4. Claim 4Independent Claim

    An electronic device, applied in an automatic doffing system which is in connection with an automated guided vehicle (AGV) and an overhead rail doffing vehicle, wherein the AGV is used to complete a dropping task of a yarn spindle product in at least one winding machine of a plurality of winding machines in a target workshop, the AGV is able to travel freely on ground without relying on a rail, the overhead rail doffing vehicle runs along a rail at a position of a certain height in the target workshop, and the AGV and the overhead rail doffing vehicle travel independently; wherein the electronic device comprises: at least one processor; and a memory connected in communication with the at least one processor; wherein the memory stores an instruction executable by the at least one processor, and the instruction, when executed by the at least one processor, enables the at least one processor to execute: determining whether the AGV is able to serve a first winding machine in the plurality

  5. Claim 5Independent Claim

    A non-transitory computer-readable storage medium, applied in an automatic doffing system which is in connection with an automated guided vehicle (AGV) and an overhead rail doffing vehicle, wherein the AGV is used to complete a dropping task of a yarn spindle product in at least one winding machine of a plurality of winding machines in a target workshop, the AGV is able to travel freely on ground without relying on a rail, the overhead rail doffing vehicle runs along a rail at a position of a certain height in the target workshop, and the AGV and the overhead rail doffing vehicle travel independently; wherein the non-transitory computer-readable storage medium stores a computer instruction thereon, and the computer instruction is used to cause the automatic doffing system to execute: determining whether the AGV is able to serve a first winding machine in the plurality of winding machines, by at least one of a), b) or c); a) determining a number L of winding machines that the AGV is abl

Technical Overview & Description

CROSS-REFERENCE TO RELATED APPLICATIONS The present application claims priority to Chinese Patent Application No. CN202311158904.2, filed with the China National Intellectual Property Administration on Sep. 8, 2023, the disclosure of which is hereby incorporated herein by reference in its entirety. TECHNICAL FIELD The present disclosure relates to the field of computer technology, and in particular, to the field of automation control. BACKGROUND In the process of doffing yarn spindle products in a winding machine, a doffing task can be completed by an Automated Guided Vehicle (AGV). However, due to the limitation of the AGV's operating speed and path, the AGV may not reach the designated position in time to complete the doffing task. This results in lower doffing efficiency of the yarn spindle products in the winding machine. Additionally, if a fully-wound yarn spindle product in the winding machine continues to wind, it may lead to tube bursting, rendering the yarn spindle products unusable and increasing their production cost. SUMMARY The present disclosure provides a doffing scheduling method and apparatus for yarn spindle product, an electronic device and a storage medium to address or mitigate one or more technical issues in the prior art. According to a first aspect, the present disclosure provides a doffing scheduling method for a yarn spindle product, applied in an automatic doffing system which is in connection with an AGV and an overhead rail doffing vehicle, the AGV and the overhead rail doffing vehicle being deployed in different vertical spaces within a target workshop, and including: determining, based on time-related information of doffing the yarn spindle product in all or part of winding machines in the target workshop, a target doffing vehicle corresponding to a first winding machine in the target workshop from the AGV and the overhead rail doffing vehicle; and scheduling the target doffing vehicle to complete a doffing task of the yarn spindle pro

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.

References Cited — Backward Prior Art (21)

Non-Patent Literature (8)

  • CN111924664B machine translation (Year: 2022).
  • CN111924659B translation (Year: 2022).
  • EP3181501B1 translation (Year: 2019).
  • Japanese Patent Office; Notice of Reasons for Rejection and translation; Japanese Application No. 2024-074723; 8 pages; dated Aug. 5, 2025.
  • The State Intellectual Property Office of People's Republic of China; CN First Office Action; CN Application No. 202311158904.2; 17 pages; dated Oct. 23, 2023.
  • The State Intellectual Property Office of People's Republic of China; Notification to Grant Patent Right for Invention; CN Application No. 202311158904.2; 6 pages; dated Jan. 9, 2025.
  • European Patent Office; Extended European Search Report; EP Application No. 24195141.7; 6 pages; dated Dec. 9, 2024.
  • Zheng, Xiaohu et al.; Spinning workshop collaborative scheduling method based on simulated annealing genetic algorithm; English Abstract; Journal of Textile Research; 6 pages; Jun. 15, 2020.