hottub.patents
US 12,596,352 B2#155964156 Most CitedActiveUnited States (USPTO)Utility

System and method for controlling a production plant consisting of a plurality of plant parts, in particular a production plant for producing industrial goods such as metallic semi-finished products

0Forward Citations (#155964156 Global)
0.0/yrCitation Velocity (#155964156 Global)
0.00Citation PageRank (#155964156 Global)
16Prior Art Cited
20Claims (2 Indep. · 18 Dep.)
1Drawings / Sheets

Abstract

A system for controlling a production plant includes a plant automation unit for monitoring and control of the production process within the production plant. A production planning system has information concerning the products to be produced. A model generator generates at least one prediction model for products produced in the production plant. The model generator takes into account the results of the monitoring of the production plant when generating the at least one prediction model. A production optimizer determines an optimized production process within the production plant on the basis of data from the plant automation unit, the production planning system, and the prediction model generated by the model generator. The production optimizer takes into account the production-related specifications of the individual plant parts. A production plant control unit generates target specifications for the plant automation unit on the basis of the optimized production process determined by the production optimizer.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 16 · Forward citations: 0.

Claims (20 — 2 Independent, 18 Dependent)

  1. Claim 1Independent Claim

    A system (1) for controlling a production plant (2) having a plurality of plant parts (3) for producing metallic semi-finished products, comprising: a plant automation unit (4) for monitoring and for open-loop and/or closed-loop control of a production process within the production plant (2), including monitoring and open-loop and/or closed-loop control of the plant parts (3); a production planning system (5) having information concerning products to be produced in the production plant (2), including target criteria for the products to be produced; a model generator (6) for generating at least one prediction model (7) for a product currently being produced in the production plant (2) and/or for the products to be produced in the future in accordance with the production planning system (5), in compliance with the target criteria for the product currently being produced or the products to be produced in the future, wherein the model generator (6) takes into account results of the monitoring of the production plant (2), including the plurality of plant parts (3), when generating the at least one prediction model (7), and wherein the at least one prediction model (7) is configured to predict compliance of the product with the target criteria, including predicting at least one of (i) an expected value of a target criterion or (ii) a probability that the target criterion lies within a defined range; a production optimizer (8) for determining an optimized production process within the production plant (2) including target specifications for control commands based on data from the plant automation unit (4), the production planning system (5), and the compliance with the target criteria predicted by the prediction model (7) generated by the model generator (6), wherein the production optimizer (8) takes into account production-related specifications of the plant parts (3) in determining the optimized production process within the production plant (2); and a production plant control unit (9) for executing the target specifications for the plant automation unit (4) based on the optimized production process determined by the production optimizer (8).

  2. Claim 2Depends on #1

    The system (1) according to claim 1, wherein each plant part (3) of the plurality of plant parts (3) comprises sensors (10) for detecting product properties, process parameters, and/or operating states within the respective plant part (3).

  3. Claim 3Depends on #1

    The system (1) according to claim 1, further comprising a central data storage unit (14) for individual components of the system (1), wherein the individual components of the system (1) can access the data and can adapt the data.

  4. Claim 4Depends on #1

    The system (1) according to claim 1, wherein the target criteria are selected from the group consisting of thickness, width, length, weight, tensile strength, yield strength, Young's modulus, elongation at break, corrosion resistance, presence or number of surface defects of various types, number of cracks on a surface or within a material, DWTT results, Charpy results, transition temperatures from ductile to brittle fractures, layer thickness of a zinc layer, tube wall thickness, eccentricity, connecting bar height, flange height, flange thickness, profile, and flatness, and wherein the at least one prediction model (7) is configured to predict the probability that the target criterion lies within the defined range.

  5. Claim 5Depends on #1

    The system (1) according to claim 1, wherein the model generator (6) generates multiple different prediction models (7), wherein the different prediction models (7) differ with regard to a creation method, original data and/or learning algorithms, and wherein the multiple different prediction models do not predict the control variables.

  6. Claim 6Depends on #5

    The system (1) according to claim 5, wherein the production optimizer (8) takes into account the prediction model (7) that provides currently best prediction for the product currently being produced in the production plant (2) and/or for the products to be produced in the future in accordance with the production planning system (5), including taking into account the target criteria.

  7. Claim 7Depends on #1

    The system (1) according to claim 1, wherein the production optimizer (8) executes an evaluation with regard to the target criteria when determining the optimized production process within the production plant (2).

  8. Claim 8Depends on #1

    The system (1) according to claim 1, wherein the production optimizer (8) determines effects of target value changes on objective specifications of the product currently being produced in the production plant (2) and/or of the product to be produced in the future in accordance with the production planning system (5).

  9. Claim 9Depends on #8

    The system (1) according to claim 8, wherein the production optimizer (8) comprises information on possible target value changes of the production plant (2), including the plant parts (3), including target value changes that can be implemented by the production plant (2), including the plant parts (3), and wherein the possible target value changes are maximum rates of change of actuator activity and/or dependencies of an adjustable variable on other variables that can also be adjusted.

  10. Claim 10Depends on #1

    The system (1) according to claim 1, wherein the production optimizer (8) optimizes the production process within the production plant (2) for a plurality of product sections.

  11. Claim 11Independent Claim

    A method for controlling a production plant (2) having of a plurality of plant parts (3) for producing metallic semi-finished products, comprising: acquiring information concerning products to be produced in the production plant (2), including target criteria for the products to be produced; monitoring a production process within the production plant (2), including within the plant parts (3); generating at least one prediction model (7) for a product currently being produced in the production plant (2) and/or for the products to be produced in the future, in compliance with target criteria for the product currently being produced or the products to be produced in the future, wherein the acquired information of the production plant (2), including the plurality of plant parts (3), is taken into account in generating the at least one prediction model (7), and wherein the at least one prediction model (7) is configured to predict compliance of the product with the target criteria, including predicting at least one of (i) an expected value of a target criterion or (ii) a probability that the target criterion lies within a defined range; determining an optimized production process within the production plant (2) including target specifications for control commands based on the acquired information concerning the products to be produced in the production plant (2), the monitoring of the production process within the production plant (2), including the plant parts (3), the compliance with the target criteria predicted by the at least one prediction model (7), and production-related parameters of the production plant (2), including production-related parameters of the plant parts (3); and executing the target specifications for an open-loop and/or closed-loop control of the production process within the production plant (2), including an open-loop and/or closed-loop control of processes within the plant parts (3).

  12. Claim 12Depends on #11

    The method according to claim 11, wherein the monitoring of the production process within the production plant (2), including within the plant parts (3), is carried out by sensors (10), and wherein the monitoring of the production process within the production plant (2), including within the plant parts (3), takes place continuously.

  13. Claim 13Depends on #11

    The method according to claim 11, further comprising storing data in a central data storage unit (14), including data with respect to the acquiring of information concerning the products to be produced in the production plant (2), including target criteria for the products to be produced, data with respect to the monitoring of the production process within the production plant (2), including the plant parts (3), data with respect to the generating the at least one prediction model (7) for the product currently being produced in the production plant (2) and/or for the products to be produced in the future, including the compliance with the target criteria for the products currently being produced or products to be produced in the future, data with respect to the determining of the optimized production process within the production plant (2) based on the acquired information concerning the products to be produced in the production plant (2), the monitoring of the production process within the production plant (2), including within the plant parts (3), of the at least one prediction model (7) and production-related parameters of the production plant (2), including production-related parameters of the plant parts (3), and/or data with respect to the generating and executing of target specifications for the open-loop and/or closed-loop control of the production process within the production plant (2), including the open-loop and/or closed-loop control of the processes within the plant parts (3).

  14. Claim 14Depends on #11

    The method according to claim 11, wherein the generating of the at least one prediction model (7) is based on methods of statistics, machine learning, or artificial intelligence, and wherein the at least one prediction model (7) is configured to predict the probability that the target criterion lies within the defined range.

  15. Claim 15Depends on #11

    The method according to claim 11, further comprising generating a plurality of different prediction models (7), wherein the different prediction models (7) differ with regard to a creation method, original data and/or learning algorithms.

  16. Claim 16Depends on #15

    The method according to claim 15, wherein the determining of the optimized production process within the production plant (2) takes into account the prediction model (7) that provides currently best prediction for the product currently being produced in the production plant (2) and/or for the products to be produced in the future, taking into account the target criteria.

  17. Claim 17Depends on #11

    The method according to claim 11, wherein in determining the optimized production process within the production plant (2), an evaluation with regard to the target criteria is carried out.

  18. Claim 18Depends on #11

    The method according to claim 11, wherein the at least one prediction model (7) determines a probability that the target criteria are within a defined range.

  19. Claim 19Depends on #11

    The method according to claim 11, wherein the determining of the optimized production process within the production plant (2) checks effects of target value changes on objective specifications of the product currently being produced in the production plant (2) and/or the product to be produced in the future.

  20. Claim 20Depends on #11

    The method according to claim 11, wherein the determining of the optimized production process within the production plant (2) takes into account information on possible target value changes of the production plant (2), including the plant parts (3), including target value changes that can be implemented by the production plant (2), including the plant parts (3), and wherein the possible target value changes are maximum rates of change of actuator activity and/or dependencies of an adjustable variable on other variables that can also be adjusted.

Technical Overview & Description

TECHNICAL FIELD The invention relates to a system and method for controlling a production plant consisting of a plurality of plant parts, in particular a production plant for producing industrial goods such as metallic semi-finished products. The invention relates in particular to production plants for producing slabs, sheets or strips, beams or tubes of metal along with their preliminary products or for carrying out individual work steps in the course of production, with which product quality must be ensured. BACKGROUND Traditionally, products are produced as a sequence of individual processes. For each of these, there are one or more technological parameters, compliance with which is to ensure the achievement of the desired product properties. Compliance with the technological regulating variables is to be ensured by the various open-loop and/or closed-loop control systems, generally by the automation system of the plant. The technological target specifications are usually determined in a sequence of theoretical considerations, simulations, laboratory tests and finally individual operational tests. Such formulations are mostly static and are not adjusted during the production sequence, or only in special cases by manual intervention. Due to non-compliance or poorly selected technological target specifications, defects arise in products within industrial production, with the result that they cannot be used for the orders for which they were originally planned or, in the worst case, cannot be put to any commercial use at all. An evaluation of production parameters during production and/or achieved qualities typically takes place manually, and a coupling between an evaluation and technological target specifications is not automated. To improve the production of products in a production plant with a plurality of plant parts, U.S. Pat. No. 10,365,640 B2 proposes determining the interrelationships between the individual plant parts by means of machine learning and deriv

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.

Non-Patent Literature (10)

  • Primetals Technologies Austria GmbH, Through-process optimization, primetals Technologies Austria GmbH, 2018.
  • Primetals Technologies, Industry 4.0 in Metals, The digitalization of steel production, MMMM New Delhi, Aug. 2016.
  • Winter, G
  • ü
  • nther.
  • “
  • Industry 4.0
  • —
  • we are a part of it.
  • ”