Abstract

An advanced system of cooperating solar module carrier robots for installing solar panels is provided. The system includes a computer vision system designed to route the cooperating solar module carrier robots to the solar tracker. The system also includes a robotic arm with a suction cup tool designed to pick up and hold a solar panel. The suction cup tool can include a set of suction cups, an actuator designed to create a vacuum in each suction cup of the set of suction cups. The suction cup tool also has an air nozzle designed to below off debris on a surface of the solar panel.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 66 · Forward citations: 0.

Claims (18 — 2 Independent, 16 Dependent)

  1. Claim 1Independent Claim

    An advanced system of cooperating solar module carrier robots for installing solar panels on a solar tracker comprising: a computer vision system designed to route the cooperating solar module carrier robots to the solar tracker; and a robotic arm with a suction cup tool designed to pick up and hold a solar panel, wherein the suction cup tool comprises: a set of suction cups; an actuator designed to create a vacuum, where each suction cup of the set of suction cups has its own vacuum; and an air nozzle designed to cooperate with the set of suction cups, wherein the air nozzle is designed to blow off debris on a surface of the solar panel.

  2. Claim 2Depends on #1

    The advanced system of cooperating solar module carrier robots of claim 1, wherein the suction cup tool is attached to the robotic arm using a quick coupler.

  3. Claim 3Depends on #1

    The advanced system of cooperating solar module carrier robots of claim 1, wherein the set of suction cups is provided in a form of two rows of suction cups.

  4. Claim 4Depends on #1

    The advanced system of cooperating solar module carrier robots of claim 1, further comprising: a first solar module carrier robot designed to carry the solar panels; and a second solar module carrier robot including the robotic arm designed to install the solar panels on the solar tracker.

  5. Claim 5Depends on #4

    The advanced system of cooperating solar module carrier robots of claim 4, wherein the first solar module carrier robot may be provided in the form of a vehicle designed to couple to a front end or a back end of the second solar module carrier robot.

  6. Claim 6Depends on #4

    The advanced system of cooperating solar module carrier robots of claim 4, wherein the first solar module carrier robot is designed with a deck large enough to hold one or more pallets of solar panels.

  7. Claim 7Depends on #6

    The advanced system of cooperating solar module carrier robots of claim 6, wherein the deck is provided in the form of a slanted deck.

  8. Claim 8Depends on #6

    The advanced system of cooperating solar module carrier robots of claim 6, wherein the first solar module carrier robot further comprises one or more sensors to determine when an amount of the solar panels on the deck is getting low.

  9. Claim 9Depends on #8

    The advanced system of cooperating solar module carrier robots of claim 8, wherein the one or more sensors are installed on the deck.

  10. Claim 10Depends on #9

    The advanced system of cooperating solar module carrier robots of claim 9, wherein the one or more sensors determine when the amount of the solar panels on the deck is getting low by weight, vision, count, or a combination thereof.

  11. Claim 11Depends on #5

    The advanced system of cooperating solar module carrier robots of claim 5, further comprising a third solar module carrier robot provided in the form of another robot designed to carry solar panels, wherein the third solar module carrier robot can be coupled to an opposite side of the end of the second solar module carrier robot relative to the first solar module carrier robot.

  12. Claim 12Independent Claim

    An advanced method for installing solar panels on a solar tracker using a system of cooperating solar module carrier robots comprising: routing the cooperating solar module carrier robots to the solar tracker using a computer vision system; picking up a solar panel with a robotic arm coupled to a first robot of the cooperating solar module carrier robots using a suction cup tool, wherein the suction cup tool includes a set of suction cups; creating a vacuum in each suction cup of the set of suction cups using an actuator, where each suction cup of the set of suction cups has its own vacuum; blowing off debris from a surface of the solar panel using an air nozzle of the suction cup tool; compressing the set of suction cups to the solar panel using the robotic arm; and holding the solar panel using the vacuum of each suction cup of the set of the suction cups.

  13. Claim 13Depends on #12

    The advanced method for installing solar panels of claim 12, further comprising: hovering the solar panel with the robotic arm at an installation position using the computer vision system.

  14. Claim 14Depends on #13

    The advanced method for installing solar panels of claim 13, further comprising: advancing the solar panel forward, rotating the solar panel, or a combination thereof; and aligning the solar panel with one or more mounting components on the solar tracker.

  15. Claim 15Depends on #12

    The advanced method for installing solar panels of claim 12, further comprising: picking up the solar panel from a second robot of the cooperating solar module carrier robots, wherein the second robot is provided in the form of a vehicle designed to couple to a front end or a back end of the second solar module carrier robot.

  16. Claim 16Depends on #15

    The advanced method for installing solar panels of claim 15, further comprising: monitoring an amount of solar panels on the second robot of the cooperating solar module carrier robots using one or more sensors.

  17. Claim 17Depends on #16

    The advanced method for installing solar panels of claim 16, wherein the one or more sensors are installed on a deck of the second robot of the cooperating solar module carrier robots, wherein the deck is designed to hold one or more pallets of the solar panels.

  18. Claim 18Depends on #12

    The advanced method for installing solar panels of claim 12, further comprising: monitoring an amount of vacuum using one or more sensors; and determining whether the solar panel is positively engaged based on the amount of vacuum.

Technical Overview & Description

CROSS-REFERENCE This application claims priority under 35 USC § 119 to U.S. patent application Ser. No. 17/206,468, filed Mar. 19, 2021, titled: “ Robotic arm cooperating with an off-road capable base vehicle, ” which claims priority to U.S. Provisional Patent Application No. 62/992,468, filed Mar. 20, 2020, titled: “ An autonomous ground vehicle for solar panel installation, ” as well as U.S. Provisional Patent Application No. 63/044,939, filed Jun. 26, 2020, titled: “ Autonomous ground vehicle for solar panel installation, ” all of which the disclosure of such is incorporated herein by reference in their entirety. TECHNICAL FIELD Embodiments of this disclosure relate generally to a robotic system for installing solar panels. BACKGROUND Today, installing and removing solar modules in a solar farm experience many problems including pausing work at night, training crews because no uniform solar tracker and solar module exists as well as the workers in the crew can change; and thus, training may need to be performed for each solar farm installation, a repetitive task performed over and over again can lead to human complacence and errors over time, and weather and bad conditions interfere with the work. SUMMARY Provided herein are various methods, apparatuses, and systems for an intelligent robotic system and task orientated processes. In an embodiment, an autonomous solar module installation platform can be used for solar module installation onto a solar tracker. The autonomous solar module installation platform can include an off-road capable base vehicle and a robotic arm, mounted on the off-road capable base vehicle, for the solar module installation onto the solar tracker. The off-road capable base vehicle and the robotic arm can communicate with each other and cooperate their movements to proceed to the solar tracker and align with the solar tracker in order for the robotic arm to pick up and lift the solar module during an installation of the solar module onto t

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.

References Cited — Backward Prior Art (66)

PatentTitleYearCitations
US 4,954,952 ARobotic arm systems1990170
US 8,360,178 B2Mobile robot201324
US 8,365,386 B2Connection process and framing device201312
US 8,635,773 B2Systems and methods of installing photovoltaic modules20144
US 8,657,991 B2Robotic solar panel string assembly process201411
US 8,688,275 B1Positive and negative obstacle avoidance system and method for a mobile robot201435
US 9,403,566 B2Robotic mobile low-profile transport vehicle201644
US 9,494,341 B2Solar tracking system employing multiple mobile robots20166
US 9,655,292 B2Methods of making photovoltaic arrays and rail systems20175
US 9,882,067 B2Installation system for photovoltaic modules20188
US 9,919,753 B2Robotic mobile low-profile transport vehicle20184
US 9,937,846 B2Vehicles and methods for magnetically managing legs of rail-based photovoltaic modules during installation20183
US 10,232,505 B2Robot for solar farms201921
US 10,277,163 B1Magnetic parking for robotic cleaner on a solar panel201922
US 10,439,550 B1System and method for positioning solar panels with automated drones201916
US 10,696,451 B2Solar panel field array support system and apparatus and method for construction use20206
US 10,926,401 B2Robot for solar farms20217
US 11,241,799 B2Solar energy array robotic assembly20226
US 11,245,353 B2Method and system for installing photovoltaic solar panels in an outdoor area202211
US 11,398,040 B2System and method for data acquisition20222
US 11,951,617 B2Robotic arm cooperating with an off-road capable base vehicle20241
US 2012027550 A1Automated installation system for and method of deployment of photovoltaic solar panels—73
US 2012152877 A1Robot for Solar Farms—217
US 2012199266 A1Robotic solar panel string assembly process—22
US 2012310444 A1Installing Terranean-Based Systems—7
US 2013019925 A1Installation System for Photovoltaic Modules—25
US 2013133172 A1Method for the automated mounting of modules on receiving devices, in particular solar modules on stands and mobile mounting device for such modules—32
US 2013146123 A1Solar Panel Tracking and Mounting System—16
US 2014246257 A1Robotic Mobile Low-Profile Transport Vehicle—63
US 2015217443 A1Robot for Solar Farms—20

Non-Patent Literature (10)

  • English translation of EP 2 267 377; retrieved via PatentTranslate located at www.epo.org. (Year: 2025).
  • European Supplementary Search Report in EP Application No. 21770761.1, dated May 2, 2024, 12 pages.
  • European Supplementary Search Report in EP Application No. 21772217.2, dated Mar. 18, 2024, 14 pages.
  • PCT International Search Report and Written Opinion in International Appln. No. PCT/US2021/023112, Jul. 8, 2021, 2 pages.
  • PCT International Search Report and Written Opinion in International Appln. No. PCT/US2021/023113, Jun. 24, 2021, 10 pages.
  • Www.comau.com,
  • “
  • Agile1500
  • ”
  • retrieved on Sep. 12, 2025, retrieved from URL