Cement mixer and multiple purpose pumper (CMMP) for land rig
Abstract
Embodiments disclosed provide a pump assembly including a first pump for delivering at least one fluid. The first pump may include a first inlet coupled to the first pump for delivering at least one first fluid to the first pump, a second inlet coupled to the first pump for delivering at least one second fluid to the first pump, a first discharge coupled to the first pump for delivering the at least one first fluid at a first pressure, and a second discharge coupled to the first pump for delivering the at least one second fluid at a second pressure. In some embodiments, the first discharge and the second discharge are isolated from each other.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 80 · Forward citations: 0.
Claims (8)
- Claim 1Independent Claim
A method performed at a wellsite, the method comprising: providing a mud pump assembly at the wellsite, the mud pump assembly including a mud pump, a mud source, a first suction line and a first discharge line, wherein the first suction line and the first discharge line are coupled to the mud pump, the first suction line is configured to supply mud, cementing fluid, and clearing fluid to the mud pump and the first discharge line is configured to discharge mud, cementing fluid, and clearing fluid from the mud pump, and wherein: the mud source is coupled to the first suction line; crossover piping is coupled to the first suction line; and a cementing fluid source and a clearing fluid source are coupled to the crossover piping; operating the mud pump to perform a mud pumping operation by pumping the mud downhole during drilling of a borehole, wherein the mud is supplied to the mud pump via the first suction line and is pumped downhole by the first discharge line; clearing the mud from the
- Claim 2Depends on #1
The method of claim 1, wherein the clearing fluid is water, and wherein clearing the mud from the mud pump assembly comprises flowing the water through the mud pump assembly.
- Claim 3Depends on #1
The method of claim 1, comprising mixing the cementing fluid via a cement mixing system.
- Claim 4Depends on #3
The method of claim 3, wherein the cement mixing system is supported on a skid, and the mud pump assembly is positioned separately from the skid.
- Claim 5Depends on #1
The method of claim 1, further comprising subsequently clearing the cementing fluid from the mud pump assembly by flowing the clearing fluid through the mud pump assembly.
- Claim 6Depends on #1
The method of claim 1, comprising monitoring, via a sensor, a flow of the mud being pumped downhole by the mud pump.
- Claim 7Depends on #1
The method of claim 1, comprising controlling, via a control unit, the mud pumping operation and the cementing operation.
- Claim 8Depends on #1
The method of claim 1, comprising: delivering electric power from a rig generator to a rig; and using the electric power to operate rig equipment and the mud pump assembly.
Technical Overview & Description
CROSS-REFERENCE TO RELATED APPLICATIONS This is a continuation application of U.S. patent application Ser. No. 17/809,185 filed on Jun. 27, 2022, now U.S. Pat. No. 12,000,236, which is a continuation application of U.S. patent application Ser. No. 15/456,050 filed on Mar. 10, 2017, now U.S. Pat. No. 11,371,314. Each of the above applications are incorporated herein by reference. BACKGROUND Exploring, drilling, and completing hydrocarbon wells are generally complicated, time consuming and ultimately very expensive endeavors. This may be especially true in the case of certain drilling and completion operations where the configuration or environment of the operation or production site presents added challenges. In certain drilling operations, the operating environment may pose several natural challenges dramatically affecting the expense of operations. In the case of land drilling, measures are often taken to curtail expenses such as keeping equipment and space for equipment to a minimum. That is, for a given land operation, any increase in the amount or types of equipment required, as well as the necessary accommodations, comes with a fairly dramatic increase in land set up and operating expenses. In certain circumstances expenses may be saved by limiting the equipment employed. However, even with certain sacrifices made in terms of equipment choices, redundancy and maximum equipment usage is desired in land operations. Like most drilling rigs, a land rig generally includes both a mud pumping assembly and a cement pumping assembly along with a host of other drilling equipment. These assemblies in particular, are alternatingly employed in completing an underground well and providing a casing therefor. That is, as a drill bit is advanced downward to form and extend a borehole below ground, the mud pumping assembly is employed to both provide fluid and remove debris with respect to a location near the advancing bit. Once the borehole has been drilled to the desired depth
Cited By — Indexed Forward Citations (0 of 0 total)
No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.
References Cited — Backward Prior Art (80)
| Patent | Title | Year | Citations |
|---|---|---|---|
| JP 4,191,513 B2 | 水素発生装置 | 2008 | 0 |
Non-Patent Literature (4)
- Office Action issued in U.S. Appl. No. 18/351,204 dated Mar. 12, 2024, 14 pages.
- Office Action issued in U.S. Appl. No. 18/351,223 dated Jun. 6, 2024, 10 pages.
- International Search Report and Written Opinion issued in International Patent application PCT/US2024/020159 on Jul. 3, 2024, 12 pages.
- International Search Report and Written Opinion issued in International Patent application PCT/US2024/020152 on Jul. 2, 2024, 11 pages.