Subsea wellhead system fatigue damage monitoring

0Forward Citations (#3496222 Global)
0.0/yrCitation Velocity (#3496222 Global)
0.00Citation PageRank (#3496222 Global)
4Prior Art Cited
20Claims (3 Indep. · 17 Dep.)
7Drawings / Sheets

Abstract

A computing system, method, and computer-readable medium includes a fatigue tracking service that assists with monitoring fatigue damage in a subsea wellhead system. The fatigue tracking service uses historical environmental data to determine a fatigue damage rate. The fatigue tracking service determines a fatigue allowance based upon the fatigue damage rate, a number of days assigned to a well operation, and a total allowable fatigue damage. The fatigue tracking service compares the fatigue allowance to measurements providing an accumulated fatigue damage to facilitate the monitoring of fatigue damage in the subsea wellhead system.

Interactive Citation Constellation Global Citation Ranking

Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 4 · Forward citations: 0.

Claims (20 — 3 Independent, 17 Dependent)

  1. Claim 1Independent Claim

    A computing system comprising: a processor; a memory; and a storage device comprising a fatigue tracking service, the fatigue tracking service comprising computer-executable instructions that perform a method comprising: obtaining, from a database in communication with the storage device, historical environmental data for an environment in which a wellhead system is located, the historical environmental data including one or more of ocean current data, wind data, and wave data; transforming the historical environmental data into a fatigue damage rate for the wellhead system, the fatigue damage rate comprising a drilling fatigue damage rate for a drilling operation and a completion fatigue damage rate for a completion operation; receiving a total maximum allowable fatigue damage for the wellhead system; assigning a number of drilling days for the drilling operation and a number of completion days for the completion operation; determining a drilling fatigue allowance and a completion fatigue allowance based upon the drilling fatigue damage rate, the completion fatigue damage rate, the total maximum allowable fatigue damage, the number of drilling days, and the number of completion days; determining an accumulated fatigue damage for the wellhead system based upon at least one of drilling fatigue damage measurements for the wellhead system and completion fatigue damage measurements for the wellhead system, wherein at least one of the drilling fatigue damage measurements and the completion fatigue damage measurements are received from one or more sensors located on at least one of a slick joint and a subsea stack coupled to the wellhead system; storing the drilling fatigue allowance, the completion fatigue allowance, and the accumulated fatigue damage in the database in communication with the storage device; and generating a graphical comparison of the accumulated fatigue damage to at least one of the drilling fatigue allowance and the completion fatigue allowance, wherein, responsive to the graphical comparison, monitoring is performed on one or more locations of highest risk of fatigue damage on the wellhead system.

  2. Claim 2Depends on #1

    The computing system of claim 1, wherein the method further comprises: adjusting the completion fatigue allowance and the completion operation for the wellhead system based upon the drilling fatigue damage measurements diverging from the drilling fatigue allowance.

  3. Claim 3Depends on #1

    The computing system of claim 1, wherein the fatigue tracking service is a machine learning model that is trained on historical fatigue damage data and the historical environmental data to predict the fatigue damage rate for the wellhead system.

  4. Claim 4Depends on #3

    The computing system of claim 3, wherein: the drilling operation comprises a first drilling phase associated with a first drilling phase number of days and a second drilling phase associated with a second drilling phase number of days; wherein the accumulated fatigue damage for the wellhead system is based upon a first drilling phase fatigue damage measurement, and wherein the method further comprises adjusting at least one of the drilling fatigue allowance and the completion fatigue allowance based upon the first drilling phase fatigue damage measurement.

  5. Claim 5Depends on #4

    The computing system of claim 4, wherein the fatigue damage rate further comprises an abandonment fatigue damage rate for an abandonment operation.

  6. Claim 6Depends on #1

    The computing system of claim 1, wherein the fatigue damage rate further comprises an intervention fatigue damage rate for an intervention operation and wherein the method further comprises: assigning a number of intervention days for the intervention operation; determining an intervention fatigue allowance based upon the intervention fatigue damage rate and the number of intervention days; determining the accumulated fatigue damage for the wellhead system by including intervention fatigue damage measurements for the wellhead system; and providing a comparison of the accumulated fatigue damage to the intervention fatigue allowance.

  7. Claim 7Depends on #6

    The computing system of claim 6, wherein the method further comprises: adjusting the intervention fatigue allowance rate based upon at least one of the drilling fatigue damage measurements, the completion fatigue damage measurements, and the intervention fatigue damage measurements.

  8. Claim 8Independent Claim

    A computer-implemented method for monitoring fatigue damage to a wellhead system, the method comprising: obtaining, from a database, historical environmental data for an environment in which a wellhead system is located, the historical environmental data including one or more of ocean current data, wind data, and wave data; transforming, by a fatigue tracking service, the historical environmental data into a fatigue damage rate for the wellhead system, the fatigue damage rate comprising a drilling fatigue damage rate for a drilling operation and a completion fatigue damage rate for a completion operation; receiving a total maximum allowable fatigue damage for the wellhead system; assigning a number of drilling days for the drilling operation and a number of completion days for the completion operation; determining a drilling fatigue allowance and a completion fatigue allowance based upon the drilling fatigue damage rate, the completion fatigue damage rate, the total maximum allowable fatigue damage, the number of drilling days, and the number of completion days; determining an accumulated fatigue damage for the wellhead system based upon at least one of drilling fatigue damage measurements for the wellhead system and completion fatigue damage measurements for the wellhead system, wherein at least one of the drilling fatigue damage measurements and the completion fatigue damage measurements are received from one or more sensors located on at least one of a slick joint and a subsea stack coupled to the wellhead system; storing the drilling fatigue allowance, the completion fatigue allowance, and the accumulated fatigue damage in the database; and generating a graphical comparison of the accumulated fatigue damage to at least one of the drilling fatigue allowance and the completion fatigue allowance, wherein, responsive to the graphical comparison, monitoring is performed on one or more locations of highest risk of fatigue damage on the wellhead system.

  9. Claim 9Depends on #8

    The method of claim 8, wherein the method further comprises: adjusting the completion fatigue allowance and the completion operation for the wellhead system based upon the drilling fatigue damage measurements diverging from the drilling fatigue allowance.

  10. Claim 10Depends on #8

    The method of claim 8, wherein the fatigue tracking service is a machine learning model that is trained on historical fatigue damage data and the historical environmental data to predict the fatigue damage rate for the wellhead system.

  11. Claim 11Depends on #10

    The method of claim 10, wherein: the drilling operation comprises a first drilling phase associated with a first drilling phase number of days and a second drilling phase associated with a second drilling phase number of days; wherein the accumulated fatigue damage for the wellhead system is based upon a first drilling phase fatigue damage measurement, and wherein the method further comprises adjusting at least one of the drilling fatigue allowance and the completion fatigue allowance based upon the first drilling phase fatigue damage measurement.

  12. Claim 12Depends on #11

    The method of claim 11, wherein the fatigue damage rate further comprises an abandonment fatigue damage rate for an abandonment operation.

  13. Claim 13Depends on #8

    The method of claim 8, wherein the fatigue damage rate further comprises an intervention fatigue damage rate for an intervention operation and wherein the method further comprises: assigning a number of intervention days for the intervention operation; determining an intervention fatigue allowance based upon the intervention fatigue damage rate and the number of intervention days; determining the accumulated fatigue damage for the wellhead by including intervention fatigue damage measurements for the wellhead system; and providing a comparison of the accumulated fatigue damage to the intervention fatigue allowance.

  14. Claim 14Depends on #13

    The method of claim 13, further comprising: adjusting the intervention fatigue allowance rate based upon at least one of the drilling fatigue damage measurements, the completion fatigue damage measurements, and the intervention fatigue damage measurements.

  15. Claim 15Independent Claim

    A non-transitory computer-readable medium comprising computer-executable instructions that when executed by a hardware processor perform a method comprising: obtaining, from a database, historical environmental data for an environment in which a wellhead system is located, the historical environmental data including one or more of ocean current data, wind data, and wave data; transforming, by a fatigue tracking service, the historical environmental data into a fatigue damage rate for the wellhead system, the fatigue damage rate comprising a drilling fatigue damage rate for a drilling operation and a completion fatigue damage rate for a completion operation; receiving a total maximum allowable fatigue damage for the wellhead system; assigning a number of drilling days for the drilling operation and a number of completion days for the completion operation; determining a drilling fatigue allowance and a completion fatigue allowance based upon the drilling fatigue damage rate, the completion fatigue damage rate, the total maximum allowable fatigue damage, the number of drilling days, and the number of completion days; determining an accumulated fatigue damage for the wellhead system based upon at least one of drilling fatigue damage measurements for the wellhead system and completion fatigue damage measurements for the wellhead system, wherein at least one of the drilling fatigue damage measurements and the completion fatigue damage measurements are received from one or more sensors located on at least one of a slick joint and a subsea stack coupled to the wellhead system; storing the drilling fatigue allowance, the completion fatigue allowance, and the accumulated fatigue damage in the database; and generating a graphical comparison of the accumulated fatigue damage to at least one of the drilling fatigue allowance and the completion fatigue allowance, wherein, responsive to the graphical comparison, monitoring is performed on one or more locations of highest risk of fatigue damage on the wellhead system.

  16. Claim 16Depends on #15

    The non-transitory computer-readable medium of claim 15, wherein the method further comprises: adjusting the completion fatigue allowance and the completion operation for the wellhead system based upon the drilling fatigue damage measurements diverging from the drilling fatigue allowance.

  17. Claim 17Depends on #15

    The non-transitory computer-readable medium of claim 15, wherein the fatigue tracking service is a machine learning model that is trained on historical fatigue damage data and the historical environmental data to predict the fatigue damage rate for the wellhead system.

  18. Claim 18Depends on #17

    The non-transitory computer-readable medium of claim 17, wherein: The drilling operation comprises a first drilling phase associated with a first drilling phase number of days and a second drilling phase associated with a second drilling phase number of days; wherein the accumulated fatigue damage for the wellhead system is based upon a first drilling phase fatigue damage measurement, and wherein the method further comprises adjusting at least one of the drilling fatigue allowance and the completion fatigue allowance based upon the first drilling phase fatigue damage measurement.

  19. Claim 19Depends on #18

    The non-transitory computer-readable medium of claim 18, wherein the fatigue damage rate further comprises an abandonment fatigue damage rate for an abandonment operation.

  20. Claim 20Depends on #15

    The non-transitory computer-readable medium of claim 15, wherein the fatigue damage rate further comprises an intervention fatigue damage rate for an intervention operation and wherein the method further comprises: assigning a number of intervention days for the intervention operation; determining an intervention fatigue allowance based upon the intervention fatigue damage rate and the number of intervention days; determining the accumulated fatigue damage for the wellhead system by including intervention fatigue damage measurements for the wellhead; and providing a comparison of the accumulated fatigue damage to the intervention fatigue allowance.

Technical Overview & Description

TECHNICAL FIELD Embodiments of the technology relate generally to tracking fatigue damage in subsea wellhead systems. BACKGROUND Offshore production of hydrocarbons requires drilling and completing wells in addition to interventions for ultimately abandoning the wells at the end of the well life cycle, which is often over 30 years. The offshore wells are sometimes located in challenging deepwater environments, requiring highly specialized subsea equipment for ensuring the well construction operation and production is carried out safely. The foundation of a subsea well is the wellhead system, which is installed during the first phase of drilling operations to provide pressure containment and structural support for the extreme loads derivate from installing temporary drilling and intervention equipment (i.e., subsea blow-out preventer stack) and permanent equipment (i.e., casing, tubing head spools, production trees). The subsea wellhead system typically includes the low-pressure housing installed with the jetted conductor casing and the high-pressure housing installed with the surface casing, locked into the low-pressure housing, typically located at 10-15 feet above the sea floor. Next, a riser extending from the floating platform is connected to the wellhead system and the remainder of the well is drilled with casing strings landed either directly on the high-pressure housing or on sub-mudline hangers. The wellhead system will support the weight of the heavy subsea blow-out preventers installed directly on the high-pressure housing for drilling operations or either the tubing head spool or production tree for completions and intervention operations. For a typical deepwater subsea well, the blow-out preventer stack may be as heavy as 700 tons with heights over 50 feet, depending on the configuration. On top of the blow-out preventers stack, long subsea riser equipment extending upward from the wellhead system is installed as conduit for the fluids used for the opera

Cited By — Indexed Forward Citations (0 of 0 total)

No indexed citing patents in this generation yet. Ingest USPTO/PatentsView bulk citation tables via patents-ingest to expand the local forward citation graph.

Non-Patent Literature (1)

  • Mercan, Bulent, et al., Soil Model Assessment for Subsea Wellhead Fatigue Using Monitoring Data, OTC-27662-MS, May 1-4, 2017.